New construction of a shelter (dual purpose building) on the territory of Scientific Lyceum No. 3 of the Poltava City Council at the address: str. Vyacheslava Chornovola, 4, Poltava


Sector
Education and science
Stream
Arrangement of civil defense protective structures (shelters) in secondary education institutions and ensuring their accessibility for all participants in the educational process
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The detailed design was developed in accordance with current regulatory documents. The purpose of the project is to construct a dual-purpose structure with the properties of an anti-radiation shelter, which is intended to: protect persons (students and staff of the lyceum) who are subject to shelter during an emergency situation, with the provision of conditions for temporary stay.

The purpose of the project

Main goal:

Creation of new facilities and services

Description of the purpose of the project and ways to achieve it

Ensuring the implementation of the Laws of Ukraine "On Education" and "On Complete General Secondary Education", creating a comfortable environment and safe conditions during the organization of the educational process

Problems and solutions resulting from project implementation

Socio-economic context

Indicator

Value

Capital expenditure per year

54983.9 thous. UAH

Number of IDP users

35 human

Number of people who will use the service

1126 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

Preschool education

Stream

Arrangement of civil defense protective structures (shelters) in secondary education institutions and ensuring their accessibility for all participants in the educational process

Strategic document

State Strategy for Regional Development for 2021–2027

Task

2.1.21 Promoting the increase in the stock of civil defense protective structures, taking into account the principles of inclusiveness and accessibility

Project objectives

Indicator
Base value
Target value

Demand for the service and its dynamics

Indicator
Year
Demand
Annual demand for services/infrastructure
28
670 human
Economic justification

Alternative technical solutions

Technical Solution 1

New construction of a shelter (dual purpose building) on the territory of Scientific Lyceum No. 3 of the Poltava City Council at the address: str. Vyacheslava Chornovola, 4, Poltava

Technical Solution 2

Repair of a rented shelter at 30 Yu. Matviychuk Street

Total costs54'993'900 UAH1'750'000 UAH
  • For preparation
  • 5'498'551 UAH250'000 UAH
  • For implementation
  • 49'485'349 UAH1'250'000 UAH
  • For operation
  • 5'000 UAH250'000 UAH
  • For closing
  • 5'000 UAH0 UAH
    Average annual costs54'983'900 UAH1'500'000 UAH
    Project duration, incl.18 months48660 months
  • Deadline for developing a FFS
  • 6 months24324 months
  • Implementation period
  • 12 months24336 months
    Service life60 months60 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active
    Rejected
    Components of a technical solution
    To components
    1
    To components
    0

    Financial justification

    Total project budget

    Total preliminary budget54'993'900 UAH1'750'000 UAH
    Capital costs54'993'900 UAH1'750'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation5'498'551 UAH250'000 UAH
    For implementation49'485'349 UAH1'250'000 UAH
    For operation5'000 UAH250'000 UAH
    For closing5'000 UAH0 UAH

    Average project cost per service recipient

    Service UnitОрієнтовна вартість проєкту
    Service Unit Cost54'983'900 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH
    Management Rationale

    Organizational events

    ResponseDefinedUndefined
    Results of the feasibility analysis
    Economic Analysis
    Social benefits and costs
    -
    Environmental benefits and costs
    -
    Indirect benefits and costs
    -