State Single Project Pipeline

Within the Public Investment Management (PIM) reform being implemented by the Government of Ukraine, a unified approach to managing public investments is being introduced at the national, regional, and local levels. In particular, a legislative framework regulating PIM matters has been approved.

The procedure for forming the Single Project Pipeline (SPP) of public investments at the state, regional, and community levels is regulated by Cabinet of Ministers Resolution No. 527 of February 28, 2025. According to the procedure, the SPP contains a list of priority projects and programs from sectoral pipelines that have undergone expert appraisal and have been approved by the Strategic or Local Investment Council as eligible for the corresponding budget financing.

The formation of the SPP at state, regional and community levels through the DREAM ecosystem ensuring transparency and enabling review, analysis, and monitoring by sectoral ministries, international partners, IFIs, and the public. This enhances opportunities for attracting funding.

Information regarding projects and programs is displayed on the State Single Project Pipeline, in accordance with the decisions of the Strategic Investment Council, which are official and subject to mandatory use. At the same time, the public API of the system may temporarily display information that differs in certain particulars from the information published on the portal; such discrepancies are of a purely technical nature and shall be remedied in the prescribed manner.

Reform
CMU Resolution No. 527

All sectors
All streams
Project code
Keyword
Project coverage area
Number of alternative technical approaches

Current set filters (Filtered result: 1)

Project code: 110825-44801377
Initiation date
Budget
Status
State level of SPP
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Second electricity transmission project

Project goal
Improving the condition of infrastructure.
Geography
All Ukraine
Initiator
PRIVATE JOINT STOCK COMPANY "NATIONAL ENERGY COMPANY "UKRENERGO"
The second electricity transmission project
Not provided
The project is aimed at ensuring: increasing the level of reliability of high-voltage substation equipment, reducing the likelihood of emergency situations in the operation of the electricity transmission system, reducing the risks of interruptions in electricity supply for the population and industry, improving conditions for increasing the efficiency of the functioning of the Unified Energy System of Ukraine by increasing the reliability of the electricity transmission system, improving the situation with reactive power compensation in networks, which will create technical conditions for closer integration of the Unified Energy System of Ukraine into the European Network of Transmission System Operators for Electricity (ENTSO-E), creating prerequisites for the effective functioning of the electricity market in Ukraine.
Budget14'870'296'703 UAH
Implementation period133 months