To ensure the coverage of the load of consumers on the left bank of Kyiv and provide capacity for new connections on the left and right banks, it is planned to implement 2 stages of measures: 1st stage (2024-2027) - creation of a 110 kV network with a capacity of 426 MW and connection of new consumers with a capacity of 192 MW on the left bank through the reconstruction of the transit line "Darnytska CHPP - Kniazhychi - Brovary" and construction of a 110 kV transit line across the Dnieper River from the Novokyivska substation to the Darnytska CHPP 2nd stage (2026-2028) - construction of a new 110 kV transit line "Odesa - Demiivska" to ensure the target reserve of transit capacity and connection of new consumers with a capacity of 168 MW on the right bank (external financing is required)
Project cost2'359'721'171 UAH
Implementation period60 months