Replacement of outdated primary equipment at substations of NPC «Ukrenergo» with the transition to modern switchgear schemes, installation of an automated process control system, creation of new transit connections, as well as the introduction of physical protection of critical elements of substations from air attacks in order to reduce the risks of emergency situations in the Unified Power System of Ukraine
Budget4'398'300'002 UAH
Implementation period54 months