General Information
Program Description
The program is aimed at modernizing urban electric transport systems in Ukrainian communities, in particular by updating infrastructure, rolling stock and management systems. The main goal of the program is to improve the quality, safety and energy efficiency of passenger transport in cities, reduce harmful emissions and bring Ukrainian cities closer to modern European mobility standards, as well as restore and modernize urban electric transport damaged as a result of military operations. The program covers a range of measures, including major repairs of tram and trolleybus lines, modernization of the contact network, traction substations, as well as the construction of new electric transport routes in areas with insufficient transport coverage. In addition, one of the key areas is the renewal of rolling stock - the purchase or modernization of trams, trolleybuses and electric buses taking into account the needs of low-mobility groups of the population, as well as the purchase of special equipment. The program will help overcome the imbalance between modern mobility requirements and the actual state of the infrastructure, ensure stable operation of electric transport - in particular in the conditions of a significant increase in the load caused by the full-scale invasion of the Russian Federation and the movement of a significant number of internally displaced persons, and will also contribute to the restoration of the competitive advantages of electric transport compared to private cars. Financing for the program can be formed from various sources: funds from international financial organizations and other credit institutions, including funds from governments of other countries, the state budget, as well as contributions from local budgets and own resources of municipal enterprises.
Strategic Case
Program Goal
Strategic Relevance of the Program
Program Objectives
Overhaul of traction substations of electric transport
0 units
315 units
Construction of depots and repair facilities
0 units
2 units
Major repairs / reconstruction of tram tracks
0 km
1546.6 km
New construction of trolleybus lines
0 km
5 km
Purchase of new trams
0 units
1684 units
Overhaul of the tram network and 600 V cable lines
0 km
1573.22 km
Deep reconstruction of tram depots
0 units
36 units
New construction of the overhead cable tram network
0 km
138.8 km
Major repairs of the trolleybus network and 600 V cable lines
0 km
3481.89 km
Deep reconstruction of the tram
0 units
50 units
Major repairs / reconstruction of trolleybus lines
0 km
3471.07 km
Overhaul of the overhead cable tram network
0 km
1546.6 km
Construction and launch of a charging station for electric buses with a minimum charging current of 25 A
0 units
40 units
Purchase of new electric buses with a carrying capacity of 80+ passengers
0 units
940 units
New tram track construction
0 km
138.8 km
Purchase of new autonomous trolleybuses
0 units
1561 units
Purchase of new trolleybuses
0 units
4165 units
Programme Sustainable Development Goals
Economic Case
Economic feasibility of the program
What are the main benefits expected from the implementation of the program for the economy, business, society, or individual industries?
Does the program objective provide for a contribution to the climate goal of mitigating the effects of climate change?
Does the program objective provide a contribution to the climate change adaptation objective: reducing the impact and/or reducing the vulnerability of an asset or population to one or more types of physical climate hazards?
Does the programme objective provide for a contribution to the climate objective of sustainable use and protection of water and marine resources?
Does the program objective provide for a contribution to the climate goal of transitioning to a circular economy?
Does the programme objective provide for a contribution to the climate objective of pollution prevention and control?
Does the program objective provide for a contribution to the climate goal of protecting and restoring biodiversity and ecosystems?
What social consequences are relevant for your program, after its implementation?
Why is it advisable to implement projects in the format of one comprehensive program, and not separately?
How will the program help strengthen other economic processes or reforms?
Program Components
Component ID
DREAM-101
Purchase of new trams
Justification
Ensuring efficient passenger transportation on routes with high passenger traffic by purchasing new trams with a carrying capacity of at least 300 people and a 100% barrier-free low-floor design, which provides full access for people with reduced mobility and high mobility for boarding and disembarking passengers.
Year
Amount
1
7'920'000'000 UAH
2
11'920'000'000 UAH
3
13'440'000'000 UAH
4
15'040'000'000 UAH
5
15'840'000'000 UAH
6
16'640'000'000 UAH
7
17'440'000'000 UAH
8
18'240'000'000 UAH
9
18'240'000'000 UAH
Component ID
DREAM-220
Major repairs of the trolleybus network and 600 V cable lines
Justification
Restoring reliable power supply to the trolleybus network by overhauling 600 V cable lines that transmit electricity from traction substations to the contact network, which is critical for the stable operation of both conventional and autonomous trolleybuses.
Year
Amount
1
469'000'000 UAH
2
491'750'000 UAH
3
865'480'000 UAH
4
1'117'690'000 UAH
5
1'788'290'000 UAH
6
3'359'720'000 UAH
7
3'359'720'000 UAH
8
3'359'720'000 UAH
9
3'359'020'000 UAH
10
6'202'840'000 UAH
Component ID
DREAM-301
Purchase of electric buses.
Justification
Promoting the decarbonization of public transport in cities without a developed electric transport network by purchasing electric buses with a working climate system (for 14 hours), a range of at least 300 km and a carrying capacity of 80 passengers, ensuring environmentally friendly and comfortable transportation.
Year
Amount
1
2'820'000'000 UAH
2
2'820'000'000 UAH
3
2'820'000'000 UAH
4
2'820'000'000 UAH
5
1'880'000'000 UAH
6
1'880'000'000 UAH
7
940'000'000 UAH
8
940'000'000 UAH
9
940'000'000 UAH
10
940'000'000 UAH
Component ID
DREAM-430
Overhaul of traction substations of electric transport
Justification
Ensuring stable and uninterrupted power supply to the tram and trolleybus network and charging infrastructure for electric buses by overhauling traction substations, which are key elements of electric transport power supply and determine its energy efficiency and reliability.
Year
Amount
1
120'000'000 UAH
2
1'080'000'000 UAH
3
2'400'000'000 UAH
4
2'400'000'000 UAH
5
2'400'000'000 UAH
6
2'400'000'000 UAH
7
2'400'000'000 UAH
8
2'100'000'000 UAH
9
1'800'000'000 UAH
10
1'800'000'000 UAH
Component ID
DREAM-150
Major repairs / reconstruction of tram tracks
Justification
Improving the safety, speed and energy efficiency of tram traffic by restoring the technical condition of worn tracks
Year
Amount
1
2'359'000'000 UAH
2
8'659'000'000 UAH
3
10'822'000'000 UAH
4
12'992'000'000 UAH
5
12'992'000'000 UAH
6
12'992'000'000 UAH
7
12'992'000'000 UAH
8
12'992'000'000 UAH
9
10'822'000'000 UAH
10
10'640'000'000 UAH
Component ID
DREAM-441
Construction of depots and repair facilities
Justification
Ensuring effective operation, maintenance and storage of modern electric transport (trams, trolleybuses, electric buses) by building new depots and repair facilities adapted to the technical requirements of new rolling stock.
Year
Amount
1
250'000'000 UAH
2
1'000'000'000 UAH
3
1'000'000'000 UAH
4
1'000'000'000 UAH
5
1'000'000'000 UAH
6
1'000'000'000 UAH
7
1'250'000'000 UAH
8
1'500'000'000 UAH
9
500'000'000 UAH
10
500'000'000 UAH
Component ID
DREAM-300
Construction and launch of a charging station for electric buses
Justification
Creating infrastructure for the full functioning of electric buses by building and launching charging stations necessary for the regular and stable operation of electric transport.
Year
Amount
1
120'000'000 UAH
2
120'000'000 UAH
3
120'000'000 UAH
4
120'000'000 UAH
5
80'000'000 UAH
6
80'000'000 UAH
7
40'000'000 UAH
8
40'000'000 UAH
9
40'000'000 UAH
10
40'000'000 UAH
Component ID
DREAM-120
Overhaul of the tram network of 600 V cable lines
Justification
Restoration of reliable power supply to tram traffic by replacing worn-out 600 V cable lines that provide power transmission from traction substations to the contact network.
Year
Amount
1
219'240'000 UAH
2
808'220'000 UAH
3
1'070'930'000 UAH
4
1'273'020'000 UAH
5
1'273'020'000 UAH
6
1'273'020'000 UAH
7
1'363'950'000 UAH
8
1'363'950'000 UAH
9
1'192'170'000 UAH
10
1'175'020'000 UAH
Component ID
DREAM-100
Deep reconstruction of trams
Justification
Extending the service life of trams, reducing energy consumption by up to 30% by replacing the control system, as well as adapting transport to the needs of low-mobility groups through the reconstruction of the interior, entrance and updating equipment in accordance with modern standards.
Year
Amount
1
80'000'000 UAH
2
80'000'000 UAH
3
80'000'000 UAH
4
80'000'000 UAH
5
80'000'000 UAH
Component ID
DREAM-151
New tram track construction
Justification
Providing access to electric public transport in new neighborhoods by expanding the tram network.
Year
Amount
3
644'000'000 UAH
4
644'000'000 UAH
5
644'000'000 UAH
6
644'000'000 UAH
7
1'624'000'000 UAH
8
1'624'000'000 UAH
9
1'946'000'000 UAH
10
1'946'000'000 UAH
Component ID
DREAM-110
Overhaul of the overhead cable tram network
Justification
Ensuring stable power supply for trams and trolleybuses by updating the contact network, as a worn-out network limits throughput and makes it impossible to fully load the rolling stock on the relevant section
Year
Amount
1
404'260'000 UAH
2
886'420'000 UAH
3
1'267'720'000 UAH
4
1'521'920'000 UAH
5
1'521'920'000 UAH
6
1'521'920'000 UAH
7
1'521'920'000 UAH
8
1'521'920'000 UAH
9
1'267'720'000 UAH
10
1'246'400'000 UAH
Component ID
DREAM-210
Major repairs / reconstruction of trolleybus lines
Justification
Ensuring reliable and stable operation of trolleybuses, including autonomous trolleybuses, through major repairs or reconstruction of the contact network, which is the main source of power during movement and recharging. The restored network will avoid overloads, ensure sufficient speed and efficient operation of electric transport.
Year
Amount
1
266'960'000 UAH
2
611'200'000 UAH
3
1'388'800'000 UAH
4
1'388'800'000 UAH
5
2'221'600'000 UAH
6
4'165'600'000 UAH
7
4'165'600'000 UAH
8
4'165'600'000 UAH
9
4'165'600'000 UAH
10
5'228'800'000 UAH
Component ID
DREAM-201.1
Purchase of new trolleybuses
Justification
Increasing the share of autonomous trolleybuses in cities with a developed trolleybus network to expand routes without additional construction of contact infrastructure. The purchase of such trolleybuses with a carrying capacity of 100–150 passengers and a 100% barrier-free low-floor design ensures full access for people with reduced mobility, quick boarding and disembarking of passengers, and from a budget point of view, a 30% lower cost compared to electric buses.
Year
Amount
4
2'340'000'000 UAH
5
2'340'000'000 UAH
6
4'680'000'000 UAH
7
7'020'000'000 UAH
8
9'360'000'000 UAH
9
10'320'000'000 UAH
9
10'770'000'000 UAH
Component ID
DREAM-111
New construction of the overhead cable tram network
Justification
Providing power supply to new tram routes by building a modern contact network with sufficient capacity for safe and stable transport operation.
Year
Amount
3
75'440'000 UAH
4
75'440'000 UAH
5
75'440'000 UAH
6
75'440'000 UAH
7
190'240'000 UAH
8
190'240'000 UAH
9
227'960'000 UAH
10
227'960'000 UAH
Component ID
DREAM-211
New construction of trolleybus lines
Justification
Optimization of the existing trolleybus route network by building new lines and intersections within the existing infrastructure to increase traffic flexibility, connection efficiency, and reduce transfers, taking into account the use of autonomous trolleybuses in new areas.
Year
Amount
6
8'000'000 UAH
7
8'000'000 UAH
8
8'000'000 UAH
9
8'000'000 UAH
10
8'000'000 UAH
Component ID
DREAM-201
Purchase of new trolleybuses
Justification
Improving the quality and accessibility of urban transportation by purchasing new trolleybuses with a carrying capacity of 100–150 passengers and a 100% barrier-free low-floor design, which ensures full access for people with reduced mobility and high speed of boarding and disembarking passengers.
Year
Amount
1
6'854'000'000 UAH
2
7'406'000'000 UAH
3
5'704'000'000 UAH
4
5'704'000'000 UAH
5
5'704'000'000 UAH
6
5'704'000'000 UAH
7
5'704'000'000 UAH
8
5'704'000'000 UAH
9
5'704'000'000 UAH
10
5'704'000'000 UAH
Component ID
DREAM-140
Deep reconstruction of tram depots
Justification
Ensuring conditions for servicing modern rolling stock through in-depth reconstruction of tram depots with the renewal of engineering infrastructure, technological equipment and adaptation to new technical standards and new types of trams
Year
Amount
1
50'000'000 UAH
2
200'000'000 UAH
3
200'000'000 UAH
4
200'000'000 UAH
5
200'000'000 UAH
6
200'000'000 UAH
7
250'000'000 UAH
8
300'000'000 UAH
9
100'000'000 UAH
10
100'000'000 UAH
Financial justification
Total estimated program cost
486'134'610'000 UAH
Estimated cost of program components
486'134'610'000 UAH
Component
Amount
Purchase of new trams
134'720'000'000 UAH
Major repairs of the trolleybus network and 600 V cable lines
24'373'230'000 UAH
Purchase of electric buses.
18'800'000'000 UAH
Overhaul of traction substations of electric transport
18'900'000'000 UAH
Major repairs / reconstruction of tram tracks
108'262'000'000 UAH
Construction of depots and repair facilities
9'000'000'000 UAH
Construction and launch of a charging station for electric buses
800'000'000 UAH
Overhaul of the tram network of 600 V cable lines
11'012'540'000 UAH
Deep reconstruction of trams
400'000'000 UAH
New tram track construction
9'716'000'000 UAH
Overhaul of the overhead cable tram network
12'682'120'000 UAH
Major repairs / reconstruction of trolleybus lines
27'768'560'000 UAH
Purchase of new trolleybuses
46'830'000'000 UAH
New construction of the overhead cable tram network
1'138'160'000 UAH
New construction of trolleybus lines
40'000'000 UAH
Purchase of new trolleybuses
59'892'000'000 UAH
Deep reconstruction of tram depots
1'800'000'000 UAH
Sources and mechanisms of financial support for the implementation of programs.
Status
Funding mechanisms
Coverage, %
Investment
Blended financing. Private financing (equity and raised funds) with state support in the form of co-financing from direct budgetary funding or grant financing. Concession, where the majority of the investments made can be reimbursed from user (consumer) payments, and the remainder (less than 50% of the project cost) is covered through grant co-financing or co-financing from the state budget (usually as non-repayable co-financing of a portion of the project’s capital expenditures during the construction period).
100%
Justification documents
What potential funding sources can be mobilized on the basis of prior agreements or intentions to cooperate (if any)
a combination of long-term loans from IFIs (EIB, EBRD), grants (Korea International Cooperation Agency (KOICA), EU donors), state and local budgets. At present, the final sources of financing for the program have not been determined. Negotiations are underway with the Korea International Cooperation Agency (KOICA) regarding the possible provision of grant funds in the amount of 5 to 15 million USD to finance infrastructure measures and rolling stock renewal, starting in 2027. In addition, the Program provides for the coverage of tax liabilities from local budgets. Other sources of financing (including attracting credit resources from international financial organizations and/or budget financing) will be determined based on the results of further negotiations with potential partners and in accordance with the capabilities of the state budget.
Management Case
Total program duration (months): 120
Approaches to project selection
Have approaches and criteria been defined for including public investment projects in the program, initiators of such projects, and their prioritization?
Organizational Measures
Program implementation
120 months
Program preparation
12 months
Risk Assessment
Risk
Probability
Degree
Strategy
Risk
Rising costs of materials and work due to inflation or exchange rate fluctuations.
Probability
Medium
Degree
Considerable
Strategy
Reduction
Risk
Insufficient institutional capacity of local governments
Probability
Medium
Degree
Considerable
Strategy
Avoidance
Risk
Delays in the delivery of equipment, materials or rolling stock due to production or logistical problems.
Probability
Medium
Degree
Critical
Strategy
Avoidance
Risk
Delay or incomplete funding from the state budget or donors.
Probability
High
Degree
Critical
Strategy
Reduction
Risk
Instability of management personnel / political changes in communities.
Probability
Medium
Degree
Considerable
Strategy
Avoidance
Risk
The need for additional approvals and environmental assessments, which may delay the completion of the work.
Probability
Low
Degree
Considerable
Strategy
Avoidance
Risk
Possible social tension among residents during construction or reconstruction (noise, street closures)
Probability
Low
Degree
Considerable
Strategy
Reduction