Construction of protective structures against damage by unmanned aerial vehicles and missiles at energy infrastructure facilities
Municipal infrastructure and services
Restoration, modernization and protection of critical infrastructure facilities to ensure their resilience to threats and the continuity of vital services
Included in the State Single Project Pipeline
General Information
Program Description
The project "Construction of protective structures against damage by unmanned aerial vehicles and missiles at energy infrastructure facilities" is aimed at protecting critically important facilities of the energy system of Ukraine.
In the conditions of the ongoing war, energy infrastructure is one of the key elements of national security, since its functioning directly affects the livelihoods of the population and the stability of the country's economy.
The project plans to erect protective structures at 22 electrical substations in different regions of the country, which will provide a comprehensive approach to protecting these facilities from attacks by unmanned aerial vehicles and missile hits.
These structures will have the ability to withstand both direct and indirect hits, which will significantly reduce the risk of large-scale accidents and power outages. The project involves the construction of protective structures at 22 electrical substations in 14 regions of Ukraine. This will help reduce the risk of infrastructure damage, ensure the stability of energy supply and increase national security.
The main objective of the project is to protect energy facilities from damage, which will minimize economic losses and increase the resilience of the energy system in war conditions.
The expected results include increasing the security of energy infrastructure, reducing the risks of power outages, as well as reducing the costs of restoring damaged facilities. The project will contribute to ensuring the stable functioning of Ukraine's energy system and strengthening its national security.
Strategic Case
Program Goal
Strategic Relevance of the Program
Program Objectives
Economic Case
Program Components
Component ID
DREAM-19-00
Construction of protective structures of the II level of protection (against damage by unmanned aerial vehicles) at energy infrastructure facilities (22 electrical substations)
Justification
The goal of the program is to ensure reliable protection of electrical substations from attacks by the aggressor, which will allow maintaining the stability of energy supply. To achieve this goal, protective structures of the II level of protection (from damage by unmanned aerial vehicles) will be built at 22 electrical substations in 14 regions of Ukraine. Constant attacks create significant risks for the power system of the entire country. The implementation of the program will allow ensuring the necessary level of security and stability of critical infrastructure. Thus, the program will allow achieving the target state in which the power system will be able to function stably even in crisis conditions.
Year
Amount
1
4'659'077'842 UAH
2
4'409'343'766 UAH
3
10'000'000'000 UAH
4
20'000'000'000 UAH
5
16'674'005'784 UAH
Component ID
DREAM-19-10
Construction of protective structures of the IIIrd level of protection (against missile attacks) at energy infrastructure facilities (22 electrical substations)
Justification
The goal of the program is to ensure reliable protection of electrical substations from attacks by the aggressor, which will allow maintaining the stability of energy supply. To achieve this goal, protective structures of the III level of protection (against missile attacks) will be built at 22 electrical substations in 14 regions of Ukraine. Constant attacks create significant risks for the power system of the entire country. The implementation of the program will allow ensuring the necessary level of security and stability of critical infrastructure. Thus, the program will allow achieving the target state in which the power system will be able to function stably even in crisis conditions.
Year
Amount
1
9'055'782'482 UAH
2
346'976'435 UAH
3
15'000'000'000 UAH
4
55'000'000'000 UAH
5
35'000'000'000 UAH
6
30'117'605'337 UAH
Financial justification
Total estimated program cost
200'262'791'646 UAH
Estimated cost of program components
200'262'791'646 UAH
Component
Amount, uah
Construction of protective structures of the II level of protection (against damage by unmanned aerial vehicles) at energy infrastructure facilities (22 electrical substations)
₴55'742'427'392
Construction of protective structures of the IIIrd level of protection (against missile attacks) at energy infrastructure facilities (22 electrical substations)
₴144'520'364'254
Sources and mechanisms of financial support for the implementation of programs.
Status
Funding mechanisms
Coverage, %
Investment
Non-repayable financing. Direct budget financing. Funded from the general fund of the state budget.
50%
Non-repayable financing. Direct budget financing. State Fund for Regional Development (SFRD), state target funds, and other revenues of the special fund of the state budget, which may be allocated for capital expenditures.
50%
Justification document
What potential funding sources can be mobilized on the basis of prior agreements or intentions to cooperate (if any)
Funds of the reserve fund of the state budget of Ukraine, funds of international financial institutions
Management Case
Organizational Measures
Project implementation
72 months
Funding attraction
6 months
Funding approval
3 months
Risk Assessment
Risk
Probability
Degree
Strategy
Risk
Lack of funding for project implementation
Probability
High
Degree
Critical
Strategy
Acceptance