General Information
Program Description
Development and expansion of border road infrastructure, namely, state border crossing points for road traffic and access roads to them within controlled border areas; Development and expansion of service areas.
Strategic Case
Program Goal
Strategic Relevance of the Program
Program Objectives
Economic Case
Economic feasibility of the program
What are the main benefits expected from the implementation of the program for the economy, business, society, or individual industries?
Does the program objective provide for a contribution to the climate goal of mitigating the effects of climate change?
Does the program objective provide a contribution to the climate change adaptation objective: reducing the impact and/or reducing the vulnerability of an asset or population to one or more types of physical climate hazards?
Does the programme objective provide for a contribution to the climate objective of sustainable use and protection of water and marine resources?
Does the program objective provide for a contribution to the climate goal of transitioning to a circular economy?
Does the programme objective provide for a contribution to the climate objective of pollution prevention and control?
Does the program objective provide for a contribution to the climate goal of protecting and restoring biodiversity and ecosystems?
What social consequences are relevant for your program, after its implementation?
Why is it advisable to implement projects in the format of one comprehensive program, and not separately?
How will the program help strengthen other economic processes or reforms?
Program Components
Component ID
DREAM-3111020
Development of the network and maintenance of public roads
Justification
Improving border infrastructure integrated into the European transport network, ensuring interoperability and bringing border infrastructure into line with the requirements of the updated EU Regulation
Year
Amount
1
574'975'210 UAH
2
6'121'371'000 UAH
3
5'389'370'830 UAH
4
2'902'564'140 UAH
Financial justification
Total estimated program cost
16'671'689'049 UAH
Estimated cost of program components
14'988'281'180 UAH
Component
Amount
Development of the network and maintenance of public roads
14'988'281'180 UAH
Additional expenses related to program preparation and implementation
1'683'407'869 UAH
Training costs
Year
Amount
1
31'465'192 UAH
Implementation costs
Year
Amount
1
1'651'942'677 UAH
Cost justification
Short description
Justification documents
Sources and mechanisms of financial support for the implementation of programs.
Status
Funding mechanisms
Coverage, %
Investment
Non-repayable financing. Grant financing from existing international support projects, international technical assistance programs, and grants. Direct expenditures.
50%
Non-repayable financing. Direct budget financing. Funded from the general fund of the state budget.
86%
Justification documents
What potential funding sources can be mobilized on the basis of prior agreements or intentions to cooperate (if any)
None available
Management Case
Total program duration (months): 60
Approaches to project selection
Have approaches and criteria been defined for including public investment projects in the program, initiators of such projects, and their prioritization?
Organizational Measures
New construction
24 months
Construction work of modernization facilities
12 months
Design of new construction projects
8 months
Design of modernization facilities
6 months
Risk Assessment
Risk
Probability
Degree
Strategy
Risk
Negative impact of construction work on the environment
Probability
Low
Degree
Critical
Strategy
Avoidance
Risk
Reduction in funding
Probability
Medium
Degree
Considerable
Strategy
Avoidance
Risk
Lack of funding
Probability
Medium
Degree
Critical
Strategy
Avoidance
Risk
Lack of funding
Probability
Medium
Degree
Critical
Strategy
Avoidance
Risk
Delay in design and construction due to difficult engineering and geological conditions; Inconsistencies in design solutions
Probability
Low
Degree
Considerable
Strategy
Avoidance
Risk
Increasing project implementation costs due to inflation, exchange rate fluctuations, and rising prices for construction materials and equipment
Probability
High
Degree
Considerable
Strategy
Acceptance
Risk
Tension among the local population due to temporary inconveniences during construction (noise, road closures, increased traffic flow)
Probability
Medium
Degree
Considerable
Strategy
Avoidance