General Information
Program Description
The purpose of the Program is to restore and develop public roads of national importance to integrate them into the European transport system and increase the level of traffic safety, speed, comfort and efficiency of transportation on them.
The implementation of the Program will make it possible to improve the transport and operational condition of public roads of national importance along the main routes, primarily along the directions of international and national transport corridors, on approaches to large cities, roads with high traffic intensity and access roads to nuclear power plants, thermal power plants, air and sea ports, military bases, elevators, railway stations, district and regional centers, territories and objects of the nature reserve fund of national importance.
Strategic Case
Program Goal
Strategic Relevance of the Program
Program Objectives
Programme Sustainable Development Goals
Economic Case
Economic feasibility of the program
What are the main benefits expected from the implementation of the program for the economy, business, society, or individual industries?
Does the program objective provide for a contribution to the climate goal of mitigating the effects of climate change?
Does the program objective provide a contribution to the climate change adaptation objective: reducing the impact and/or reducing the vulnerability of an asset or population to one or more types of physical climate hazards?
Does the programme objective provide for a contribution to the climate objective of sustainable use and protection of water and marine resources?
Does the program objective provide for a contribution to the climate goal of transitioning to a circular economy?
Does the programme objective provide for a contribution to the climate objective of pollution prevention and control?
Does the program objective provide for a contribution to the climate goal of protecting and restoring biodiversity and ecosystems?
What social consequences are relevant for your program, after its implementation?
Why is it advisable to implement projects in the format of one comprehensive program, and not separately?
How will the program help strengthen other economic processes or reforms?
Program Components
Component ID
DREAM-3
Major repairs of public roads of state importance
Justification
Today, the Recovery Agency has 416 unfinished capital repair facilities. The cost of work to complete the initiated projects is over 70 billion UAH. Component 3 of this Program provides for the repair of part of these facilities over the next 3 years, in particular those that are a priority for the state, taking into account the needs of the country during the war period. Given the significant number of projects (facilities) for the capital repair of national roads, both initiated and planned, it is advisable to develop a Program with components that will include the relevant projects for the capital repair of national roads.
Year
Amount
1
22'673'163'500 UAH
2
84'667'011'200 UAH
3
124'156'258'000 UAH
Component ID
DREAM-2
Reconstruction of public roads of national importance
Justification
Today, the Reconstruction Agency has 82 unfinished reconstruction projects. The cost of work to complete the initiated projects is over 30 billion UAH. Component 2 of this Program provides for the completion of some of these projects over the next 3 years, in particular those that are a priority for the state, taking into account the needs of the country during the war period. Given the significant number of projects (objects) for the reconstruction of national highways, both initiated and planned, it is advisable to develop a Program with components that will include relevant projects for the reconstruction of national highways.
Year
Amount
1
2'050'000'000 UAH
2
7'300'000'000 UAH
3
11'147'265'000 UAH
Component ID
DREAM-1
New construction of public roads of national importance
Justification
Today, the Reconstruction Agency has 77 unfinished new construction projects. The cost of work to complete the initiated projects is over 130 billion UAH. Component 1 of this Program provides for the completion of some of these projects over the next 3 years, in particular those that are a priority for the state, taking into account the needs of the country during the war period. Given the significant number of projects (objects) for the construction of national highways, both initiated and planned, it is advisable to develop a Program with components that will include relevant projects for the construction of national highways.
Year
Amount
1
1'950'000'000 UAH
2
6'500'000'000 UAH
3
10'748'399'700 UAH
Financial justification
Total estimated program cost
271'192'097'400 UAH
Estimated cost of program components
271'192'097'400 UAH
Component
Amount
Major repairs of public roads of state importance
231'496'432'700 UAH
Reconstruction of public roads of national importance
20'497'265'000 UAH
New construction of public roads of national importance
19'198'399'700 UAH
Cost justification
Short description
Justification documents
Sources and mechanisms of financial support for the implementation of programs.
Status
Funding mechanisms
Coverage, %
Investment
Non-repayable financing. Direct budget financing. State Fund for Regional Development (SFRD), state target funds, and other revenues of the special fund of the state budget, which may be allocated for capital expenditures.
100%
Justification documents
What potential funding sources can be mobilized on the basis of prior agreements or intentions to cooperate (if any)
Funds of the State Budget of Ukraine, in particular the special fund of the state budget - the state road fund
Management Case
Total program duration (months): 36
Approaches to project selection
Have approaches and criteria been defined for including public investment projects in the program, initiators of such projects, and their prioritization?
Organizational Measures
Execution of construction works for new construction, reconstruction and major repairs of public roads of state importance
36 months
Execution of works on designing new construction, reconstruction and major repairs of public roads of state importance, including design for future periods
36 months
Risk Assessment
Risk
Probability
Degree
Strategy
Risk
In 2024–2025, all revenues from the state road fund were directed to the general fund of the state budget to strengthen the army and strengthen the defense of the State. There is a risk that the situation will repeat in 2026.
Probability
High
Degree
Critical
Strategy
Acceptance
Risk
Currently, there has been a decrease in the production capacities of contracting organizations in recent years. Another technical risk is the specificity of technological processes during road works (duration of the construction season).
Probability
Medium
Degree
Considerable
Strategy
Avoidance
Risk
A change in the country's political leadership may affect the vector of policy regarding the restoration of highways
Probability
Low
Degree
Minor
Strategy
Reduction