Reconstruction of the power grid system by installing a solar power plant at 21 Ya. Shynkarenka St.


Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, with the introduction of alternative energy sources
Maturity level
82
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project involves the reconstruction of the power grid system with the implementation of a modern solar power plant (SPP), which will allow partially or fully to meet the needs of the facility/community in electricity from renewable energy sources.

The purpose of the project

Main Goal:

Creation of new facilities and services

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

The goal of the project is to ensure reliable, economical and environmentally safe energy supply by reconstructing the power grid system with the installation of a solar power plant, which will allow: to reduce electricity consumption costs; to increase the energy independence and security of the facility/community; to reduce greenhouse gas emissions and negative environmental impact; to create a modern infrastructure for sustainable development of the territory.

Problems and solutions resulting from project implementation

High dependence on centralized energy supply Problem: frequent outages, risk of outages, dependence on tariff fluctuations. Solution: installation of a solar power plant that provides partial or full autonomy, as well as a backup energy source. 2. Significant electricity costs Problem: annual tariff increases create an additional financial burden on the budget/consumers. Solution: use of own generation from renewable sources, which will reduce electricity costs in the long term. 3. Low energy efficiency of existing networks Problem: energy losses due to outdated infrastructure. Solution: modernization of networks and equipment when integrating solar power plants, which reduces losses and increases efficiency.

Socio-economic context

Indicator

Value

Population in the geographical area of influence of the project

8000 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Water supply and sanitation

Stream

Restoration, development and modernization of centralized water supply and wastewater infrastructure, with the introduction of alternative energy sources

Strategic document

Стратегія розвитку територіальної громади

Task

2.1.2 Modernization of water supply, sewage, and heating and water supply with the introduction of alternative energy sources

Project objectives

Project objectives were not specified by the initiator
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
fin analysis solar e.docx
30.09.2025
14:08:10 UTC

Alternative technical solutions

Technical Solution 1

construction of a solar power plant

Technical Solution 2

electrical network repair

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)2'000'000 UAH300'000 UAH
For preparation500'000 UAH50'000 UAH
For implementation1'500'000 UAH250'000 UAH
Project operation and closure cost1'700'000 UAH200'000 UAH
For operation1'300'000 UAH170'000 UAH
For closing400'000 UAH30'000 UAH
Average annual costs3'700'000 UAH0 UAH
Project duration, incl.17 months24 months
Deadline for developing a FFS5 months12 months
Implementation period12 months12 months
Service life60 months12 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
1
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget3'700'000 UAH500'000 UAH
Project cost (preparation and implementation)2'000'000 UAH300'000 UAH
For preparation500'000 UAH50'000 UAH
For implementation1'500'000 UAH250'000 UAH
Project operation and closure cost1'700'000 UAH200'000 UAH
For operation1'300'000 UAH170'000 UAH
For closing400'000 UAH30'000 UAH
Чи була під час уточнення орієнтовного бюджету використана Методика розрахунку вартості публічного інвестиційного проєкту, затверджена наказом Міністерства фінансів України №316 від 23.06.2025 р.?
Yes
[Response was provided in the Investment Feasibility Study]
Чи була під час розрахунку орієнтовного бюджету використана Методика розрахунку вартості публічного інвестиційного проєкту, затверджена наказом Міністерства фінансів України №316 від 23.06.2025 р.?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Average project cost per service recipient

Service Unitлюд
Service Unit Cost462 UAH

Profitability of the project

Is the project expected to generate income?YesNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
No – analysis not performed

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
None of the options are applicable
Does the team have experience implementing similar projects?
Partially, we have limited experience

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
No, I need help.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

Updating existing documentation regarding the preparation of the feasibility study
[Response was provided in the Investment Feasibility Study]
Updating existing documentation regarding the preparation of design and estimate documentation (DED)
[Response was provided in the Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
08/10/2025SP-L-081025-7FF911C9Community SPInvestment Feasibility StudyInclude--
27/11/2025SPP-L-271125-61A31BFACommunity SPPInvestment Feasibility StudyInclude-82