Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform


Sector
Education and science
Stream
Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Maturity level
65
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SP
Implementation
Completion

General information

Description of the project

providing secondary education institutions with teaching aids and equipment 

The purpose of the project

Main Goal:

Improving the quality of services

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

providing high-quality, modern and accessible general secondary education "New Ukrainian School"

Problems and solutions resulting from project implementation

quality education

Socio-economic context

Indicator

Value

Number of people who will use the service

539 units

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform

Strategic document

State Strategy for Regional Development for 2021–2027

Task

1 Improving the material and technical base of educational institutions, ensuring the quality of educational services, particularly in rural areas.

Project objectives

Indicator
Base value
Target value
providing educational equipment
29 units
32 units

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
economic analysis.xlsx
01.10.2025
05:48:38 UTC

Alternative technical solutions

Technical Solution 1

providing multimedia equipment

Technical Solution 2

ensuring accessible general secondary education

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)2 UAH1'800'001 UAH
For preparation1 UAH1 UAH
For implementation1 UAH1'800'000 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Average annual costs1 UAH1 UAH
Project duration, incl.24 months24 months
Deadline for developing a FFS12 months12 months
Implementation period12 months12 months
Service life12 months60 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Unsuccessful

[The technical approach was analyzed and considered for implementation but was not selected as the final option.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

No

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget4 UAH1'800'003 UAH
Project cost (preparation and implementation)2 UAH1'800'001 UAH
For preparation1 UAH1 UAH
For implementation1 UAH1'800'000 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unitштштуки
Service Unit Cost1'800'000 UAH3'400 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesYes

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
11/11/2025SP-L-111125-705EC072Community SPInvestment Feasibility StudyInclude--
24/11/2025SPP-L-241125-2F0EB308Community SPPInvestment Feasibility StudyCancellation of the decision to include in a joint venture-65