Purchase of a specialized vehicle for organizing the delivery of food and food raw materials to educational institutions of the Koblivka Village Council
Sector
Education and science
Stream
Optimization of the community's educational institution system (purchase of buses for educational institutions)
Maturity level
82
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The purpose of the project
Main Goal:
Improving the quality of services
Description of the purpose of the project and ways to achieve it
• Ensuring stable logistics by organizing the delivery of food and food raw materials to educational institutions by the Koblivka Village Council's own specialized transport.
• Strengthening safety control during product transportation in compliance with the requirements of food quality legislation
Problems and solutions resulting from project implementation
• Minimizing the risks of temperature violations during delivery, which is a critical factor for the food safety of schoolchildren.
Socio-economic context
Indicator
Value
Number of people who will use the service
840 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Optimization of the community's educational institution system (purchase of buses for educational institutions)
Strategic document
Стратегія розвитку територіальної громади
Task
2.6.1 Optimization of the community's educational institution system
Project objectives
Indicator
Base value
Target value
Number of people who will use the service
0 human
840 human
Project Sustainable Development Goals
Economic justification
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
None of the options are applicable
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
None of the options are applicable
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
None of the options are applicable
Does the project provide for improving women's access to services?
None of the options are applicable
Are civil society organizations representing women and vulnerable groups included in the consultation process?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Alternative technical solutions
Technical Solution 1
Purchase of a specialized vehicle for organizing the delivery of food and food raw materials to educational institutions of the Koblivka Village Council
Technical Solution 2
Purchase of a specialized vehicle for organizing the delivery of food and food raw materials to educational institutions of the Koblivka Village Council
Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)535'000 UAH535'000 UAH
For preparation5'000 UAH5'000 UAH
For implementation530'000 UAH530'000 UAH
Project operation and closure cost465'000 UAH4'015'000 UAH
For operation450'000 UAH4'000'000 UAH
For closing15'000 UAH15'000 UAH
Average annual costs450'000 UAH0 UAH
Project duration, incl.5 months4 months
Deadline for developing a FFS2 months2 months
Implementation period3 months2 months
Service life120 months120 months
Target indicatorsDefined Defined
Technical Solution Status
Active
[The technical approach was selected for further detailed analysis or implementation.]
Rejected
[The technical approach was not selected for further detailed analysis or implementation.]
Components of a technical solution
Commercial Justification
Supplier and contractor market assessment
Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Is the project of interest to small and medium-sized enterprises?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Will the project involve national or international suppliers and contractors?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Has an analysis of available procurement options been conducted for the technical solution?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Total preliminary budget1'000'000 UAH4'550'000 UAH
Project cost (preparation and implementation)535'000 UAH535'000 UAH
For preparation5'000 UAH5'000 UAH
For implementation530'000 UAH530'000 UAH
Project operation and closure cost465'000 UAH4'015'000 UAH
For operation450'000 UAH4'000'000 UAH
For closing15'000 UAH15'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Investment Feasibility Study]
Average project cost per service recipient
Service Unitгривня
Service Unit Cost450'000 UAH
Profitability of the project
Is the project expected to generate income?NoNo
Availability of services
Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Source and MechanismYesNo
Funding Sources
Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH
Public-private partnership
Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character
[Response was provided in the Preliminary Investment Feasibility Study]
Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs
Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?
Finalization of existing documentation for the preparation of a preliminary feasibility study
[Response was provided in the Investment Feasibility Study]
Updating existing documentation regarding the preparation of the feasibility study
[Response was provided in the Investment Feasibility Study]
Project Approval History
DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
03/02/2026SP-L-030226-DF34022CCommunity SPInvestment Feasibility StudyNot approvednot included by mistake-
03/02/2026SP-L-030226-EF0E93A5Community SPInvestment Feasibility StudyInclude--
10/02/2026SPP-L-100226-DBEEA76FCommunity SPPInvestment Feasibility StudyIncludeApprove and include in the community's EPP82