Major repairs through comprehensive thermal modernization of the building of the Gorodetsky Lyceum of the Sarny City Council, on Kolomyets Avenira St., building 154a, in the village of Gorodetsky, Sarny district, Rivne region


Sector
Municipal infrastructure and services
Stream
Improving energy efficiency in public buildings
Maturity level
91
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project envisages carrying out thermal modernization measures for the building of the Gorodetsky Lyceum, which will include a complex of works to replace the heating system, replace windows and doors, insulate the facade, replace and insulate the roof

The purpose of the project

Main Goal:

Introducing innovations and energy-efficient solutions

Secondary Goal:

Improving the quality of services

Description of the purpose of the project and ways to achieve it

Comprehensive thermal modernization of an educational institution building to achieve significant energy savings, improve comfort for students and staff, and reduce negative environmental impact.

Problems and solutions resulting from project implementation

Excessive energy consumption, insufficient wall insulation, outdated windows and doors

Socio-economic context

Indicator

Value

Number of people who will use the service

415 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Urban planning and landscaping

Stream

Improving energy efficiency in public buildings

Strategic document

Long-term Strategy for Building Thermal Modernization until 2050

Task

Strategic Goal 6 Strategic Goal 6 to the OPERATIONAL PLAN of measures for the implementation in 2024-2026 of the Long-term Strategy for Thermal Modernization of Buildings for the Period Until 2050 Increasing energy efficiency in public buildings

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Аналіз даних щодо витрат на енергоносії за попередні роки
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
416 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?

No
[Response was provided in the Investment Feasibility Study]

Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?

Conducting an EIA is not required.
[Response was provided in the Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Were consultations held with representatives of target groups to take into account gender equality issues in the project?

No consultations were held with target groups.
[Response was provided in the Investment Feasibility Study]

Have the gender risks and social impacts of the project been assessed?

None of the options are applicable

Are there management and institutional mechanisms in place to ensure gender equality?

Not provided for by the project
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
Economic justification Gorodets.docx
02.02.2026
14:26:00 UTC

Alternative technical solutions

Technical Solution 1

Major repairs through comprehensive thermal modernization of the building of the Gorodetsky Lyceum of the Sarny City Council, on Kolomyets Avenira St., building 154a, in the village of Gorodetsky, Sarny district, Rivne region

Technical Solution 2

Use of the school building in its existing condition

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)90'407'522 UAH2 UAH
For preparation1'395'194 UAH1 UAH
For implementation89'012'328 UAH1 UAH
Project operation and closure cost52'120'001 UAH39'090'001 UAH
For operation52'120'000 UAH39'090'000 UAH
For closing1 UAH1 UAH
Average annual costs1'042'400 UAH0 UAH
Project duration, incl.17 months2 months
Deadline for developing a FFS1 month1 month
Implementation period16 months1 month
Service life600 months360 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

What procurement strategy was chosen for the project implementation, and what justifies its feasibility in the context of the market and project objectives?
Open bidding

[Response was provided in the Investment Feasibility Study]

What approaches are planned to be used to ensure transparency, competition, and efficiency in the procurement process?
система Прозоро

[Response was provided in the Investment Feasibility Study]

What types of procurement procedures are envisaged by the project (open tender, negotiated procedure, competitive dialogue, etc.)?
Open competitive bidding

[Response was provided in the Investment Feasibility Study]

Pre-market engagement
Analysis of similar projects

[Response was provided in the Investment Feasibility Study]

Potential market participants
На ринку наявні кваліфіковані виконавці

[Response was provided in the Investment Feasibility Study]

Market readiness assessment
На ринку наявні кваліфіковані виконавці

[Response was provided in the Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget142'527'523 UAH39'090'003 UAH
Project cost (preparation and implementation)90'407'522 UAH2 UAH
For preparation1'395'194 UAH1 UAH
For implementation89'012'328 UAH1 UAH
Project operation and closure cost52'120'001 UAH39'090'001 UAH
For operation52'120'000 UAH39'090'000 UAH
For closing1 UAH1 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitСередня вартість проєкту на одного отримувача послуги
Service Unit Cost8'355 UAH

Profitability of the project

Is the project expected to generate income?NoNo
Is the project self-sustaining?No

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project management structure defined: working group, chair, project team?
No

[Response was provided in the Investment Feasibility Study]

What categories of experts and consultants have already been involved at the project preparation stage?
Technical experts

[Response was provided in the Investment Feasibility Study]

Are there plans to involve experts and consultants for further implementation of the project?
No

[Response was provided in the Investment Feasibility Study]

Organizational events

ResponseDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project require preparation assistance from Project Preparation Programs (PPF)?

None of the options are applicable

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable
Need for financing

Does the project require additional funding for preparation?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
04/02/2026SP-L-040226-A781616ECommunity SPInvestment Feasibility StudyCancellation of the decision to include in a joint venture--
05/02/2026SP-L-050226-DB97A89CCommunity SPInvestment Feasibility StudyInclude--
11/02/2026SPP-L-110226-253B5691Community SPPInvestment Feasibility StudyInclude-91