Major repairs and improvements to part of the territory of the Tyachiv district hospital at 48 Neresenska Street in the city of Tyachiv, Zakarpattia region
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The project "Major repairs and improvement of part of the territory of the Tyachiv District Hospital at 48 Neresenska Street in the city of Tyachiv, Zakarpattia Oblast" is being implemented to improve the infrastructure and safe conditions for using the territory of the healthcare facility. The customer/beneficiary of the works is the KNP "Tyachiv District Hospital" of the Tyachiv City Council, Zakarpattia Oblast. The facility belongs to the CC1 impact class. The key component of the project is the installation of a storm sewer network for rainwater drainage with the connection of storm drains and drainage trays, using PVC SN4 pipes. The implementation of the project will ensure orderly drainage and increase the comfort and safety of movement for patients, visitors and staff on the hospital territory.
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
15032 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Ensuring access to quality medical care through the development and modernization of medical infrastructure facilities
Strategic document
Strategy for the Development of the Healthcare System until 2030
Task
4 Development of a concept, implementation plan and formation of a network of healthcare institutions for integrated primary health care, aimed at concentrating medical resources and services in order to ensure access to quality medical care at the level of territorial communities
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs and improvements to part of the territory of the Tyachiv district hospital at 48 Neresenska Street in the city of Tyachiv, Zakarpattia region
Technical Solution 2
Partial improvement of the territory
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Is the project expected to generate income?
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]