Modernization of the street lighting system by installing alternative sources of electricity in the city of Bilhorod-Dnistrovskyi, Odessa region


Sector
Municipal infrastructure and services
Stream
Modernization of the street lighting system by installing alternative sources of electricity in the city of Bilhorod-Dnistrovskyi, Odessa region
Maturity level
79
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project involves modernizing the street lighting system of the city of Bilhorod-Dnistrovskyi by installing alternative sources of electricity (solar panels with LED lights). This will increase energy efficiency, reduce electricity costs, reduce CO₂ emissions, and ensure reliable and environmentally friendly lighting of the city's streets.

The purpose of the project

Main Goal:

Increasing the even distribution of resources

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

The goal is to increase the energy efficiency and environmental friendliness of street lighting in the city of Bilhorod-Dnistrovskyi by introducing alternative sources of electricity. The project aims to reduce electricity costs, ensure stable street lighting and reduce CO₂ emissions, while increasing the safety and comfort of residents.

Problems and solutions resulting from project implementation

Outdated lamps and high electricity costs lead to uneconomical consumption of resources and poor lighting quality. The implementation of the project will improve the quality of lighting, reduce electricity costs, increase energy efficiency and environmental friendliness of the system, as well as provide reliable light in the evening and at night on all streets of the city.

Socio-economic context

Indicator

Value

Population in the geographical area of influence of the project

45000 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Urban planning and landscaping

Stream

Modernization of the street lighting system by installing alternative sources of electricity in the city of Bilhorod-Dnistrovskyi, Odessa region

Strategic document

Стратегія розвитку територіальної громади

Task

2.4.4. Ensure modernization and innovative development of the community's engineering infrastructure

Project objectives

Indicator
Base value
Target value
the number of light points
0 units
2880 units

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Strategy.pdf
29.10.2025
13:40:06 UTC

Alternative technical solutions

Technical Solution 1

Modernization of the street lighting system by installing alternative sources of electricity in the city of Bilhorod-Dnistrovskyi, Odessa region

Technical Solution 2

Hybrid system (solar panels + grid + batteries)

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)2'070'000 UAH4'300'000 UAH
For preparation120'000 UAH100'000 UAH
For implementation1'950'000 UAH4'200'000 UAH
Project operation and closure cost250'000 UAH200'000 UAH
For operation250'000 UAH150'000 UAH
For closing0 UAH50'000 UAH
Average annual costs250'000 UAH0 UAH
Project duration, incl.6 months8 months
Deadline for developing a FFS2 months2 months
Implementation period4 months6 months
Service life120 months120 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget2'320'000 UAH4'500'000 UAH
Project cost (preparation and implementation)2'070'000 UAH4'300'000 UAH
For preparation120'000 UAH100'000 UAH
For implementation1'950'000 UAH4'200'000 UAH
Project operation and closure cost250'000 UAH200'000 UAH
For operation250'000 UAH150'000 UAH
For closing0 UAH50'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitМодернізація системи вуличного освітлення шляхом встановлення альтернативних джерел електричної енергії міста Білгород-Дністровський Одеської області
Service Unit Cost2'320'000 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds2'320'000 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Partially, we have limited experience

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
12/11/2025SP-L-121125-B1E133D2Community SPInvestment Feasibility StudyInclude--
08/12/2025SPP-L-081225-1B59D579Community SPPInvestment Feasibility StudyInclude-79