Modernization of educational spaces and updating of the material and technical base of academic lyceums


Sector
Education and science
Stream
Modernization of educational spaces and updating of the material and technical base of academic lyceums
Maturity level
88
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project "Equipment of a physics classroom at the Novoukrainsk Lyceum "Leader"" provides for the creation of a modern educational space worth 1,500,000 UAH in order to improve the quality of the educational process and develop students' scientific and technical competencies.

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Secondary Goal:

Improving the quality of services

Description of the purpose of the project and ways to achieve it

Improving the level of physics teaching, developing students' practical skills, stimulating interest in natural and mathematical sciences, improving the results of external examinations/NMT and preparing for further studies in higher education institutions. Main activities: - purchase of modern laboratory equipment, measuring and demonstration equipment; - equipping the classroom with multimedia tools (interactive panel, projector); - software - provision of furniture; - creation of conditions for conducting experiments, experiments and scientific research activities of students

Problems and solutions resulting from project implementation

Modern equipment and teaching aids ensure high-quality experiments and practical classes. Equipping with interactive panels, computers and a projector increases the clarity and effectiveness of training. Conducting experiments and working with laboratory equipment form practical competencies. The modern format of classes stimulates interest in physics and increases the level of academic achievements. A learning environment is created for high-quality preparation for testing and scientific research activities.

Socio-economic context

Indicator

Value

Number of people who will use the service

184 human

Number of IDP users

10 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Modernization of educational spaces and updating of the material and technical base of academic lyceums

Strategic document

Стратегія розвитку територіальної громади

Task

54 Promote the continuous adaptation of educational services to the modern needs of local children and youth

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Аналіз кількості учнів, які вивчають фізику. Прогноз динаміки контингенту учнів на 3–5 років. Вивчення результатів ЗНО та ДПА з фізики (рівень знань). Анкетування учнів, батьків і вчителів щодо потреб у сучасному обладнанні. Опитування педагогів щодо ефективності існуючої матеріально-технічної бази
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
184 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Economic analysis of the project.docx
30.09.2025
06:20:04 UTC

Alternative technical solutions

Technical Solution 1

Modernization of the educational space and updating of the material and technical base (physics room) of the Novoukrainsk Lyceum "Leader"

Technical Solution 2

Mobile or modular laboratories

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)1'500'500 UAH2'000'500 UAH
For preparation500 UAH500 UAH
For implementation1'500'000 UAH2'000'000 UAH
Project operation and closure cost5'001 UAH5'001 UAH
For operation5'000 UAH5'000 UAH
For closing1 UAH1 UAH
Average annual costs155'000 UAH0 UAH
Project duration, incl.2 months2 months
Deadline for developing a FFS1 month1 month
Implementation period1 month1 month
Service life120 months60 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget1'505'501 UAH2'005'501 UAH
Project cost (preparation and implementation)1'500'500 UAH2'000'500 UAH
For preparation500 UAH500 UAH
For implementation1'500'000 UAH2'000'000 UAH
Project operation and closure cost5'001 UAH5'001 UAH
For operation5'000 UAH5'000 UAH
For closing1 UAH1 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitОтримувач послуги
Service Unit Cost8'152 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds1'500'000 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
06/10/2025SP-L-061025-49C8BC66Community SPInvestment Feasibility StudyInclude--