New construction of a protective civil defense structure on the territory of Radomyshl Lyceum No. 3 of Zhytomyr region at 14 Shkilnoye Str., Radomyshl, Zhytomyr district, Zhytomyr region


Sector
Education and science
Stream
Ensuring the safety of participants in the educational process by creating or modernizing the protective infrastructure of ZZSO institutions
Maturity level
80
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SP
Implementation
Completion

General information

Description of the project

The project involves the construction of a PRU, P-1, protection class-1000, a separate building, with connection to existing electricity, water, sewage networks and autonomous generation in compliance with safety and inclusive accessibility requirements. Dual use of the premises is also possible, since the project provides for the premises of a first-aid post, cafeteria, lecture hall, etc. The implementation of the project will make it possible to improve the provision of educational services and the quality of the educational process, in particular its safety and accessibility, including for low-mobility population groups - 16 separately equipped places, physical safety of entering and moving around the facility, staying in a shelter. An autonomous stay of 48 hours is provided.

The purpose of the project

Main Goal:

Improving the quality of services

Secondary Goal:

Ensuring inclusiveness and equal opportunities

Description of the purpose of the project and ways to achieve it

protection of the population, namely students and employees, from ionizing radiation and means of destruction in emergency situations. ensuring uninterrupted access of individuals to educational services, organization of full-time education, improving the quality of the educational process

Problems and solutions resulting from project implementation

The implementation of the project will enable the security and accessibility of educational services

Socio-economic context

Indicator

Value

Number of people who will use the service

260 units

Number of employees of the institution/institution/organization

34 units

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Ensuring the safety of participants in the educational process by creating or modernizing the protective infrastructure of ZZSO institutions

Strategic document

State Strategy for Regional Development for 2021–2027

Task

1,.21 Promoting the increase in the stock of civil defense protective structures, taking into account the principles of inclusiveness and accessibility.

Project objectives

Indicator
Base value
Target value
Safety and quality improvement of educational services
13 units
14 units
protection of the population
13 units
14 units

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

експертне судження
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

No
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
100 units
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Lyceum 3.pdf
21.10.2025
08:11:38 UTC

Alternative technical solutions

Technical Solution 1

civil defense protective structure

Technical Solution 2

anti-radiation shelter

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)40'099'520 UAH2 UAH
For preparation39'999'520 UAH1 UAH
For implementation100'000 UAH1 UAH
Project operation and closure cost22'223 UAH2 UAH
For operation22'222 UAH1 UAH
For closing1 UAH1 UAH
Average annual costs1 UAH0 UAH
Project duration, incl.24 months48 months
Deadline for developing a FFS12 months12 months
Implementation period12 months36 months
Service life360 months240 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Unsuccessful

[The technical approach was analyzed and considered for implementation but was not selected as the final option.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget40'121'743 UAH4 UAH
Project cost (preparation and implementation)40'099'520 UAH2 UAH
For preparation39'999'520 UAH1 UAH
For implementation100'000 UAH1 UAH
Project operation and closure cost22'223 UAH2 UAH
For operation22'222 UAH1 UAH
For closing1 UAH1 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Preliminary Investment Feasibility Study]
No
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unitштшт
Service Unit Cost39'000 UAH1 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesYes

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
11/11/2025SP-L-111125-29F1A8B3Community SPInvestment Feasibility StudyInclude--
11/01/2026SP-N-110126-114ECF59State SPInvestment Feasibility StudyInclude--
24/11/2025SPP-L-241125-E240E5AFCommunity SPPInvestment Feasibility StudyInclude-80