Major renovation of the basement of a residential building for use as the simplest shelters at 3 Polyarna St. in the Obolonskyi district of Kyiv


Sector
Public safety
Stream
Забезпечення доступності житла з безпечними, комфортними умовами проживання
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Regional level of SP
Implementation
Completion

General information

Description of the project

The project involves the overhaul of a basement for use as a simple shelter in a residential building within the framework of the Comprehensive Target Program for Economic and Social Development of the City of Kyiv for 2024-2026. The investment project is vitally necessary and expedient without alternative, its effectiveness should be assessed according to social and humanitarian criteria, which are priorities in the context of ongoing military aggression. The overhaul of the basement will ensure safe conditions for people in cases of threat to their life and health. 

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Secondary Goal:

Improving the quality of services

Description of the purpose of the project and ways to achieve it

Project goal: To ensure the functionality and safety of the shelter. Project goal: to protect and preserve human life.

Problems and solutions resulting from project implementation

Prior to the implementation of the project, the basement, which is planned to be used as the simplest shelter, has a number of critical shortcomings that can be eliminated by carrying out a major repair of the specified facility. The project will provide for the repair and arrangement of the simplest shelter, which will ensure the safe stay of people during air raids, which is critically important for preserving life and health.

Socio-economic context

Indicator

Value

Number of people who will use the service

200 human

Strategic Case

Strategic feasibility of the project

Sector

Public safety

Subsector

Civil defense

Stream

Забезпечення доступності житла з безпечними, комфортними умовами проживання

Strategic document

Стратегія розвитку територіальної громади

Task

2.1. Сприяння збільшенню фонду захисних споруд цивільного захисту та забезпечення їх відповідності критеріям постійної готовності для захисту населення з урахуванням принципів інклюзивності та безбар’єрності

Project objectives

Project objectives were not specified by the initiator

Demand for the service and its dynamics

Indicator
Year
Demand
Annual demand for services/infrastructure
1
73000 human
Economic justification

Documents

Name
Date
built shelter 3 Polyarna St._cropped.pdf
30.04.2026
05:53:58 UTC

Alternative technical solutions

Technical Solution 1

Major renovation of the basement of a residential building for use as the simplest shelters at 3 Polyarna St. in the Obolonskyi district of Kyiv

Technical Solution 2

New construction of a radiation shelter on the adjacent territory at 3 Polyarna St. in the Obolonskyi district of Kyiv

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)4'500'000 UAH18'108'156 UAH
For preparation55'612 UAH200'000 UAH
For implementation4'444'388 UAH17'908'156 UAH
Project operation and closure cost0 UAH590'000 UAH
For operation0 UAH560'000 UAH
For closing0 UAH30'000 UAH
Average annual costs450'000 UAH0 UAH
Project duration, incl.10 months10 months
Deadline for developing a FFS2 months4 months
Implementation period8 months6 months
Service life120 months960 months
Target indicatorsDefined Not defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Pending

[The project initiator has not taken any decision about this alternative technical approach.]

Components of a technical solution
To components
0
To components
0

Financial justification

Total project budget

Total preliminary budget4'500'000 UAH18'698'156 UAH
Project cost (preparation and implementation)4'500'000 UAH18'108'156 UAH
For preparation55'612 UAH200'000 UAH
For implementation4'444'388 UAH17'908'156 UAH
Project operation and closure cost0 UAH590'000 UAH
For operation0 UAH560'000 UAH
For closing0 UAH30'000 UAH

Average project cost per service recipient

Service UnitСередня вартість проєкту на одного отримувача
Service Unit Cost22'500 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH
Management Rationale

Risk assessment

Technical riskDefinedUndefined

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
30/04/2026SP-R-300426-B101B901Regional SPInvestment Feasibility StudyInclude--