General information
Description of the project
The project involves major repairs of the water supply network in the village of Novofedorivka, Mykolaiv district, Mykolaiv region.
The implementation of the project is aimed at ensuring a stable water supply for the population.
The project plans to: completely replace worn-out pipelines with polyethylene pipes from PE100SDR17, upgrade equipment at wells (pumps, control elements and electrical networks from existing entry points), provide water supply from three wells (No. 120-g91, No. 216, No. 128), install water collection wells with the ability to connect up to 10 subscribers in each, install distribution combs with 1¾ taps for connecting subscribers, installation of water metering units.
The result will be an uninterrupted supply of high-quality drinking water for 945 residents of the village and infrastructure facilities, a reduction in accident rates and operating costs.
The purpose of the project
Main goal:
Improving the condition of infrastructure
Secondary goal:
Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capacity
450 m3
Number of people who will use the service
700 human
Population in the geographical area of influence of the project
945 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Providing the population with high-quality drinking water (water supply and wastewater treatment)
Strategic document
Стратегія розвитку територіальної громади
Task
2.1.3.1 Construction, major repairs and reconstruction of water supply and drainage networks of settlements and community recreation areas
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
статистичні дані, офіційні норми водоспоживання та санітарні стандарти, лабораторні дослідження води, дані ОМС
Does the demand forecast take into account the latest demographic and economic forecasts?
Демографічні дані, зміна чисельності населення, аналіз стану соціально-економічного розвитку.
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Зменшення втрат води за рахунок оновлення мереж, повторне використання водних ресурсів та зниження потреби в аварійних роботах дозволяє скоротити споживання матеріалів і енергії, подовжити строк експлуатації інфраструктури та мінімізувати відходи.
Підвищує стійкість системи водопостачання до екстремальних погодних умов та сезонних навантажень.
Ризик забруднення ґрунтів і підземних вод зменшується шляхом заміни зношених мереж та усунення витоків, що запобігає потраплянню забруднюючих речовин у довкілля та покращує санітарний стан території.
Зменшення втрат води, покращення якості питної води та раціональне використання водних ресурсів.
Негативний вплив на ґрунти та природні екосистеми зменшується за рахунок заміни зношених мереж і ліквідації витоків води, що знижує підтоплення, деградацію земель та неконтрольоване забруднення.
Капітальний ремонт водопровідної мережі забезпечує стабільне постачання якісної води, зменшує втрати води та підвищує ефективність системи, що сприяє раціональному використанню води, збереженню екосистем та покращенню санітарних умов.
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Вириті траншеї створюють небезпеку пересування, тимчасові труднощі у доступі до води. Огородження траншей, попереджувальні знаки, підвіз води.
Обмеження доступу до об'єктів торгівлі під час виконання робіт; втрата доходу для підприємців через перекриття вулиць. Створити графік робіт; альтернативні точки обслуговування населення або обхідні маршрути.
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Консультації щодо розташування колодязів, графіків подачі води та заходів безпеки під час проведення робіт, для захисту інтересів жінок і вразливих груп.
Alternative technical solutions
Technical Solution 1
Major repairs of the water supply network in the village of Novofedorivka, Mykolaiv district, Mykolaiv region
Technical Solution 2
Current repairs of the water supply network in the village of Novofedorivka, Mykolaiv district, Mykolaiv region
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Investment Feasibility Study]
Ринок підрядників і постачальників у регіоні достатньо розвинений, що забезпечує конкуренцію та високу якість пропозицій.
[Response was provided in the Investment Feasibility Study]
Проєкт привабливий для малих і середніх підприємств завдяки можливості виконання будівельних робіт.
[Response was provided in the Investment Feasibility Study]
Проєкт передбачає використання місцевих постачальників та підрядників, оскільки капітальний ремонт водопостачання можна повністю забезпечити регіональними компаніями.
[Response was provided in the Investment Feasibility Study]
Проводився аналіз на Prozorro, а також здійснені запити до підрядників, які здійснюють даний вид робіт, з метою оцінки їхніх можливостей та вартості робіт.
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Is the project expected to generate income?
Availability of services
[Response was provided in the Investment Feasibility Study]
k65cvvd5-60l8-4516-ar7p-j5j3zlqp214d
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Team competencies
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Development and examination of the PCD
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Оцінка впливу на довкілля та відповідності екологічним вимогам
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]