New construction of a protective structure (radiation shelter) for Andrushivka Lyceum No. 2 of the Andrushivka City Council


Sector
Education and science
Stream
Arrangement of civil defense protective structures (shelters) in secondary education institutions
Project Status
Preliminary Investment Feasibility Study
Entry into Portfolio
State level of SP
Investment Feasibility Study
Implementation
Completion

General information

Description of the project

The construction of a protective structure (radiation shelter) with a capacity of 100 people with two evacuation exits and one inclined lift for MGN will ensure a temporary stay in a safe place for participants in the training process, allowing the continuation of the training process when this is impossible in conditions of direct threat.  

The purpose of the project

Main goal:

Increasing compliance with modern standards

Secondary goal:

Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Improving the quality of services

Description of the purpose of the project and ways to achieve it

Creating a safe environment for students, teachers, and staff of an educational institution during emergencies, including military operations, shelling, man-made or natural disasters. The construction of a new protective structure on the territory of the institution will allow for faster creation of safe conditions during threats.

Problems and solutions resulting from project implementation

The capacity of the shelters will be increased. The project takes into account all the conditions for low-mobility groups of the population. The shelter is dual-purpose, so it can also be used for educational purposes.

Socio-economic context

Indicator

Value

Number of people who will use the service

100 human

Number of IDP users

20 human

Number of employees of the institution/institution/organization

20 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Arrangement of civil defense protective structures (shelters) in secondary education institutions

Strategic document

Стратегія розвитку територіальної громади

Task

Task 3.1.3 Conditions have been created for the safe stay of participants in the educational process, including persons with disabilities, in educational institutions of the urban territorial community.

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Аналіз демографічних даних, збільшення показника кількості здобувачів освіти з ООП

Has data from external sources been used in the demand assessment?

Yes

Аналіз прогнозованої мережі ЗЗСО громади

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes

Зростання кількості здобувачів освіти в закладі та зростання кількості дітей з ООП

Indicator
Year
Demand
Annual demand for services/infrastructure
1
800 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]

1

Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Preliminary Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Transition to a circular economy
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Preliminary Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

The project may result in the forced displacement of women, men and other gender groups or loss of access to resources
[Response was provided in the Preliminary Investment Feasibility Study]
Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]
Other gender risks
[Response was provided in the Preliminary Investment Feasibility Study]
There are risks of impaired mobility or safety for women, men and other gender groups during construction/operation
[Response was provided in the Preliminary Investment Feasibility Study]
There is a risk of reduced economic opportunities for women, men and other gender groups (e.g. loss of jobs or retail outlets)
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]
Other benefits from project implementation
[Response was provided in the Preliminary Investment Feasibility Study]
Envisaged training or advanced training for women in the private sector
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Alternative technical solutions

Technical Solution 1

New construction of a civil defense protective structure (radiation shelter) at Andrushivskyi Lyceum No. 2

Technical Solution 2

Construction of a civil defense structure for the ZZSO

Total costs64'070'000 UAH75'500'000 UAH
  • For preparation
  • 270'000 UAH300'000 UAH
  • For implementation
  • 13'500'000 UAH15'000'000 UAH
  • For operation
  • 50'000'000 UAH60'000'000 UAH
  • For closing
  • 300'000 UAH200'000 UAH
    Average annual costs500'000 UAH600'000 UAH
    Project duration, incl.7 months10 months
  • Deadline for developing a FFS
  • 3 months4 months
  • Implementation period
  • 4 months6 months
    Service life1200 months1800 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget64'070'000 UAH75'500'000 UAH
    Capital costs64'070'000 UAH75'500'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation270'000 UAH300'000 UAH
    For implementation13'500'000 UAH15'000'000 UAH
    For operation50'000'000 UAH60'000'000 UAH
    For closing300'000 UAH200'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitКількість отримувачів
    Service Unit Cost140'000 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

    No
    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the project require preparation assistance from Project Preparation Programs (PPF)?

    Development of a full feasibility study;
    [Response was provided in the Preliminary Investment Feasibility Study]
    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Preliminary Investment Feasibility Study]
    Development of design and estimate documentation (DED);
    [Response was provided in the Preliminary Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Preliminary Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Preliminary Investment Feasibility Study]
    Other
    [Response was provided in the Preliminary Investment Feasibility Study]
    Need for financing

    Does the project require additional funding for preparation?

    No
    [Response was provided in the Preliminary Investment Feasibility Study]