CAPITAL REPAIR OF HIGHWAY BRIDGE #6 OVER THE RUSANIVSKY CANAL, CONNECTING PLEKHANOV STREET WITH ENTHUSIASTIV STREET


Sector
Transport Sector
Stream
Модернізація та розвиток вулично-шляхової мережі та штучних споруд міста (мости та шляхопроводи) з урахуванням принципів доступності та гендерних підходів
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Regional level of SP
Implementation
Completion

General information

Description of the project

According to the results of the last comprehensive inspection of the bridge, the technical condition of the structure is determined as - inoperable (Condition 5). The structure requires major repairs. The remaining resource of the structure has been exhausted. Postponing the work may lead to unforeseen consequences.
As part of the implementation of the work, it is planned to carry out work on the installation of new bridge deck structures and span structures, repair of supports, repair of approaches to the structure, and landscaping of the adjacent territory.
Carrying out major repairs will allow the structure to be brought into working order, ensuring safe and uninterrupted traffic for all road users.

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

As part of the implementation of the works, it is planned to carry out work on the installation of new bridge deck structures and span structures, repair of supports, repair of approaches to the structure, and improvement of the surrounding area.

Problems and solutions resulting from project implementation

Socio-economic context

Indicator

Value

Capital expenditure per year

20000 thous. UAH

Strategic Case

Strategic feasibility of the project

Sector

Transport Sector

Subsector

Road transport and road infrastructure

Stream

Модернізація та розвиток вулично-шляхової мережі та штучних споруд міста (мости та шляхопроводи) з урахуванням принципів доступності та гендерних підходів

Strategic document

Стратегія розвитку територіальної громади

Task

Завдання 2.3 Модернізація та розвиток вуличношляхової мережі та штучних споруд міста (мости та шляхопроводи) з урахуванням принципів доступності та гендерних підходів

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Documents

Name
Date
Order of the State Tax Inspectorate No. 37 dated 06.02.2026_on the Address List_for dream.pdf
29.04.2026
07:41:50 UTC

Alternative technical solutions

Technical Solution 1

CAPITAL REPAIR OF HIGHWAY BRIDGE #6 OVER THE RUSANIVSKY CANAL, CONNECTING PLEKHANOV STREET WITH ENTHUSIASTIV STREET

Technical Solution 2

Reconstruction of road bridge No. 6 over the Rusanivskyi Canal, connecting Plekhanova Street with Entuziastov Street

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)137'209'515 UAH180'000'000 UAH
For preparation8'075'871 UAH10'500'000 UAH
For implementation129'133'644 UAH169'500'000 UAH
Project operation and closure cost0 UAH0 UAH
Average annual costs6'860'476 UAH0 UAH
Project duration, incl.33 months45 months
Deadline for developing a FFS19 months25 months
Implementation period14 months20 months
Service life240 months240 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Financial justification

Total project budget

Total preliminary budget137'209'515 UAH180'000'000 UAH
Project cost (preparation and implementation)137'209'515 UAH180'000'000 UAH
For preparation8'075'871 UAH10'500'000 UAH
For implementation129'133'644 UAH169'500'000 UAH
Project operation and closure cost0 UAH0 UAH
For operation0 UAH0 UAH
For closing0 UAH0 UAH

Average project cost per service recipient

Service UnitОрієнтовна загальна кошторисна вартість по об`єкту
Service Unit Cost137'209'515 UAH

Profitability of the project

Is the project expected to generate income?NoNo
Is the project self-sustaining?No

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
29/04/2026SP-R-290426-62017072Regional SPInvestment Feasibility StudyInclude--