Reconstruction of the power supply system with the installation of a photovoltaic station with an electricity storage system of the Bilokrynytsia Support Gymnasium at the address: Bila Krynytsia village, Beryslav district, Kherson region
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The project plans to comprehensively reconstruct the power supply system of the Bilokrynytsia Support Gymnasium with the implementation of modern solutions in the field of renewable energy. In particular, it is planned to install a 50 kW photovoltaic power plant and an electricity storage system, which will ensure stable and autonomous power supply to the educational institution. The project is aimed at solving the problems of unstable and emergency power supply, which negatively affect the continuity of the educational process, the safety of students and employees, as well as the functioning of the institution in conditions of military threats. The lack of backup power sources limits the possibility of using the gymnasium as a safe space and a community support facility during emergencies. The expected results of the project are to increase the energy independence and sustainability of the educational institution, ensure uninterrupted operation of critical systems, reduce electricity costs from the local budget, and reduce carbon emissions through the use of renewable energy sources. The implementation of the project will contribute to the creation of safe and stable conditions for learning and the strengthening of the social infrastructure of the community.
The purpose of the project
Main goal:
Introducing innovations and energy-efficient solutions
Secondary goal:
Increasing compliance with modern standards, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of employees of the institution/institution/organization
30 human
Number of people who will use the service
225 human
Number of IDP users
40 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Development and Reconstruction of Subnational Infrastructure
Stream
Development and rehabilitation of municipal infrastructure of subnational governments
Strategic document
Стратегія розвитку територіальної громади
Task
1.1.2 Ensure the development of cultural and local heritage protection centers that form local self-awareness and bind residents to their places of residence
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
Alternative technical solutions
Technical Solution 1
Reconstruction of the power supply system with the installation of a photovoltaic station with an electricity storage system of the Bilokrynytsia Support Gymnasium at the address: Bila Krynytsia village, Beryslav district, Kherson region
Technical Solution 2
Installing a diesel (or gasoline) electric generator
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]