Major repairs of a non-residential building for the establishment of a stationary care unit for the elderly and adults with disabilities at Horishnia Street, 30, Girske village, Stryi district, Lviv region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project plans to carry out a complex of construction and repair works, including: restoration and insulation of facades, roofs, ceilings and floors; replacement of windows, doors, engineering networks (electricity, water supply, drainage, heating, ventilation); arrangement of sanitary and hygienic premises, living rooms, kitchen and household areas; ensuring barrier-free conditions and accessibility for people with disabilities; improvement of the surrounding area. The implementation of the project is aimed at improving the social infrastructure of the community, creating comfortable and safe living conditions and care for the elderly and adults with disabilities.
The purpose of the project
Main Goal:
Improving the quality of services
Secondary Goal:
Improving the equality of wealth distribution
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
30 human
Strategic Case
Strategic feasibility of the project
Sector
Social sector
Subsector
Social services
Stream
Creating conditions for independent living for people with disabilities and the elderly by developing supported living services
Strategic document
Strategy for Reforming Psychiatric and Other Residential Institutions and for the Deinstitutionalization of Care for Adults with Disabilities and Older Persons until 2034
Task
Strategic goal 2 Promoting comprehensive reform of long-term care for people with disabilities and older people by developing people's capacity to acquire, restore or maintain daily living skills
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs of a non-residential building for the establishment of a stationary care unit for the elderly and adults with disabilities at Horishnia Street, 30, Girske village, Stryi district, Lviv region
Technical Solution 2
organization of day or mobile care services for the elderly and people with disabilities.
[The technical approach was selected for further detailed analysis or implementation.]
[The project initiator has not taken any decision about this alternative technical approach.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]