Overhaul of the hot water supply system with the installation of autonomous sources (solar vacuum collectors) of the Koblevo preschool educational institution (nursery-kindergarten) "Sonechko" at the address: Mykolaiv region, Mykolaiv district, village of Koblevo, 7 Stepova St.


Sector
Education and science
Stream
Thermal modernization of public buildings
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

The purpose of the project

Main goal:

Introducing innovations and energy-efficient solutions

Secondary goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

The project involves modernizing the hot water supply (DHW) system by replacing worn-out pipes and installing solar vacuum collectors for autonomous water heating. This increases energy efficiency, ensures uninterrupted hot water supply, and significantly reduces costs for traditional energy sources (electricity or gas) through the use of renewable energy.

Problems and solutions resulting from project implementation

Need for financing to complete the project

Socio-economic context

Indicator

Value

Number of people who will use the service

200 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Thermal modernization of public buildings

Strategic document

Стратегія розвитку територіальної громади

Task

2.3.1 Reconstruction of social and humanitarian institutions taking into account modern energy-efficient technologies

Project objectives

Indicator
Base value
Target value
Number of people who will use the service
0 human
200 human

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

The project may result in the forced displacement of women, men and other gender groups or loss of access to resources
[Response was provided in the Investment Feasibility Study]
Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other gender risks
[Response was provided in the Investment Feasibility Study]
There are risks of impaired mobility or safety for women, men and other gender groups during construction/operation
[Response was provided in the Investment Feasibility Study]
There is a risk of reduced economic opportunities for women, men and other gender groups (e.g. loss of jobs or retail outlets)
[Response was provided in the Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other benefits from project implementation
[Response was provided in the Investment Feasibility Study]
Envisaged training or advanced training for women in the private sector
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
Economic analysis of solar panels.docx
27.01.2026
11:19:08 UTC

Alternative technical solutions

Technical Solution 1

Overhaul of the hot water supply system with the installation of autonomous sources (solar vacuum collectors) of the Koblevo preschool educational institution (nursery-kindergarten) "Sonechko" at the address: Mykolaiv region, Mykolaiv district, village of Koblevo, 7 Stepova St.

Technical Solution 2

Repair of the hot water supply system with the installation of autonomous sources (solar vacuum collectors) of the Koblevo preschool educational institution (nursery-kindergarten) "Sonechko" at the address: Mykolaiv region, Mykolaiv district, village of Koblevo, 7 Stepova St.

Total costs5'184'295 UAH5'184'298 UAH
  • For preparation
  • 150'000 UAH150'000 UAH
  • For implementation
  • 3'657'670 UAH3'657'673 UAH
  • For operation
  • 1'371'625 UAH1'371'625 UAH
  • For closing
  • 5'000 UAH5'000 UAH
    Average annual costs54'865 UAH54'865 UAH
    Project duration, incl.14 months4 months
  • Deadline for developing a FFS
  • 11 months1 month
  • Implementation period
  • 3 months3 months
    Service life300 months300 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    No

    [Response was provided in the Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    No

    [Response was provided in the Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget5'184'295 UAH5'184'298 UAH
    Capital costs5'184'295 UAH5'184'298 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation150'000 UAH150'000 UAH
    For implementation3'657'670 UAH3'657'673 UAH
    For operation1'371'625 UAH1'371'625 UAH
    For closing5'000 UAH5'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service Unitгривня
    Service Unit Cost25'922 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    No – analysis not performed

    [Response was provided in the Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Other
    [Response was provided in the Investment Feasibility Study]
    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]