Major repairs of the water main from the Zhdanivka water intake to the village of Velyka Oleksandrivka, Beryslav district, Kherson region


Sector
Municipal infrastructure and services
Stream
Development and rehabilitation of municipal infrastructure of subnational governments
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SP
Implementation
Completion

General information

Description of the project

The project "Overhaul of the water supply from the Zhdanivka water intake to the village of Velyka Oleksandrivka, Beryslav district, Kherson region" involves the execution of work on the preparation of design and estimate documentation and the implementation of a project to carry out a major repair of the existing water supply network, in order to improve the quality of water supply services provided to residents of the settlement territorial community

The purpose of the project

Main goal:

Improving the condition of infrastructure

Secondary goal:

Increasing compliance with modern standards, Increasing compliance with modern standards, Improving the equality of wealth distribution, Introducing innovations and energy-efficient solutions, Improving the quality of services

Description of the purpose of the project and ways to achieve it

Problems and solutions resulting from project implementation

The existing water supply system does not meet modern needs (as of 2026) for the following reasons: Constant leaks and surges create a risk of limiting consumers' access to water supply services. Resource shortage: The decrease in the amount of high-quality water in Ukraine requires the implementation of accurate metering systems and minimizing losses, which is impossible based on the current damaged infrastructure. Conclusion: Major repairs with the replacement of pipes with modern ones and the installation of new pumping equipment is the only way to ensure stable and safe water supply in accordance with the 2026 standards

Socio-economic context

Indicator

Value

Number of people who will use the service

5200 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Development and Reconstruction of Subnational Infrastructure

Stream

Development and rehabilitation of municipal infrastructure of subnational governments

Strategic document

Стратегія розвитку територіальної громади

Task

1.1.2 Ensure the development of cultural and local heritage protection centers that form local self-awareness and bind residents to their places of residence

Project objectives

Indicator
Base value
Target value
Length of replaced water supply network
0 km
6.5 km
Share of repaired water supply network
0 %
100 %

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

При оцінці попиту для проєкту реконструкції водопровідної мережі у 2026 році застосовується комплексна методологія, що поєднує нормативний, ретроспективний та прогнозний аналізи.

Has data from external sources been used in the demand assessment?

Yes

Публічна кадастрова карта України (для уточнення меж забудови та планів розвитку території), Система DREAM (Аналіз аналогічних проектів у регіоні та громадах для порівняння вартості та показників ефективності)

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes

про прогнозі попиту враховано останні демографічні та економічні показники

Indicator
Year
Demand
Annual demand for services/infrastructure
1
100 %
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Investment Feasibility Study]

не застосовується до вказаного проекту

Climate change adaptation
[Response was provided in the Investment Feasibility Study]

проектом передбачається адаптація до зміни клімату

Pollution prevention and control
[Response was provided in the Investment Feasibility Study]

проектом передбачається запобігання та контроль забруднення навколишнього середовища, екологічної системи

Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

not applicable

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]

так, проєктом передбачається захист і відновлення біорізноманіття та екосистем

Climate change mitigation
[Response was provided in the Investment Feasibility Study]

not applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]

у результаті реалізації проекта передбачається захист і відновлення біорізноманіття та екосистеми

Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]

в результаті реалізації проекту передбачається запобігання та контроль забруднення

Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

The project may result in the forced displacement of women, men and other gender groups or loss of access to resources
[Response was provided in the Investment Feasibility Study]
Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other gender risks
[Response was provided in the Investment Feasibility Study]
There are risks of impaired mobility or safety for women, men and other gender groups during construction/operation
[Response was provided in the Investment Feasibility Study]
There is a risk of reduced economic opportunities for women, men and other gender groups (e.g. loss of jobs or retail outlets)
[Response was provided in the Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other benefits from project implementation
[Response was provided in the Investment Feasibility Study]
Envisaged training or advanced training for women in the private sector
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
Justification of financial support mechanisms.docx
27.01.2026
13:25:21 UTC

Alternative technical solutions

Technical Solution 1

Major repairs of the water main from the Zhdanivka water intake to the village of Velyka Oleksandrivka, Beryslav district, Kherson region

Technical Solution 2

Current repairs of the water supply network of the Zhdanivka water intake

Total costs36'330'001 UAH1'202'001 UAH
  • For preparation
  • 930'000 UAH2'000 UAH
  • For implementation
  • 27'000'000 UAH300'000 UAH
  • For operation
  • 8'400'000 UAH900'000 UAH
  • For closing
  • 1 UAH1 UAH
    Average annual costs420'000 UAH450'000 UAH
    Project duration, incl.15 months4 months
  • Deadline for developing a FFS
  • 1 month1 month
  • Implementation period
  • 14 months3 months
    Service life240 months24 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Investment Feasibility Study]

    проєкт залучить достатню кількість учасників торгів, щоб забезпечити реальну конкуренцію, яка спонукатиме учасників торгів мислити інноваційно та максимізувати якість своїх пропозицій

    Is the project of interest to small and medium-sized enterprises?
    No

    [Response was provided in the Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, both national and international

    [Response was provided in the Investment Feasibility Study]

    проект залучить національних або міжнародних постачальників та підрядників

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Investment Feasibility Study]

    в процесі підготовки проекту було проведено аналіз доступних варіантів закупівель для технічного рішення

    Financial justification

    Total project budget

    Total preliminary budget36'330'001 UAH1'202'001 UAH
    Capital costs36'330'001 UAH1'202'001 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation930'000 UAH2'000 UAH
    For implementation27'000'000 UAH300'000 UAH
    For operation8'400'000 UAH900'000 UAH
    For closing1 UAH1 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service Unitодиниця
    Service Unit Cost27'000'000 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    No – analysis not performed

    [Response was provided in the Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Other
    [Response was provided in the Investment Feasibility Study]
    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]