Reconstruction of the existing premises with adaptation for temporary stay of the ZDO No. 52 "Veseli stezhynky" at the address: 58018, Chernivtsi, Poletaeva Fedora St., 3
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The project involves the reconstruction of the existing premises in order to adapt it for the temporary stay of children in the preschool educational institution No. 52 "Vesely stezhynky" at the address: Chernivtsi, st. Poletaeva Fedora, 3.
The project plans to carry out construction and repair works, modernize engineering networks, ensure proper sanitary and hygienic and safety conditions, as well as create a barrier-free and functional educational space.
The project is aimed at solving the problem of insufficient adaptability of existing premises for the safe and comfortable stay of children during emergencies and increased risks.
The implementation of the project will ensure the continuity of the educational process, improve the conditions of stay of children and employees of the institution, as well as increase the level of readiness of the institution to function in martial law conditions.
Expected results: creation of a safe, adapted and regulatory-compliant space for the temporary stay of preschool children, increasing the level of protection of children and staff, improving the quality of preschool education and social stability of the community.
The purpose of the project
Main goal:
Meeting demand
Secondary goal:
Increasing compliance with modern standards, Increasing compliance with modern standards, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
15 human
Number of employees of the institution/institution/organization
55 human
Number of people who will use the service
280 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
Preschool education
Stream
Ensuring access to quality education through the development and modernization of educational infrastructure facilities
Strategic document
Стратегія розвитку територіальної громади
Task
Increasing energy efficiency and energy independence of urban development
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of the existing premises with adaptation for temporary stay of the ZDO No. 52 "Veseli stezhynky" at the address: 58018, Chernivtsi, Poletaeva Fedora St., 3
Technical Solution 2
Location of a modular building on the territory of a preschool educational institution
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Is the project expected to generate income?
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]