Major repairs of basements of non-residential buildings of buildings No. 2R-5, 1R-3, R-2 with the installation of a protective civil defense structure (dual-purpose structure with the protective properties of an anti-radiation shelter) of the BMR "BOGUSLAVSKA TSL" at 27 Franka Ivana Street, Boguslav city, Obukhiv district, Kyiv region.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves major repairs of the protective structure at the KNP BMR "Bohuslavska TsL" at 27 Franka Ivana Street, Bohuslav city. The implementation is due to the unsatisfactory technical condition of the building's basements, water supply and sewage networks and requires the creation of safe, energy-efficient and modern conditions for the stay of the institution's patients and staff in the protective structure during air alarms.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Ensuring inclusiveness and equal opportunities
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of employees of the institution/institution/organization
256 human
Number of people who will use the service
5640 human
Population in the geographical area of influence of the project
24150 human
Number of IDPs in the geographical area of impact of the project
1176 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Arrangement of civil defense structures (shelters) in healthcare facilities (PHCs)
Strategic document
Стратегія розвитку територіальної громади
Task
3.2.2 Renovation of civil defense facilities and implementation of energy-efficient technologies in healthcare facilities
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Major repairs of basements of non-residential buildings of buildings No. 2R-5, 1R-3, R-2 with the installation of a protective civil defense structure (dual-purpose structure with the protective properties of an anti-radiation shelter) of the BMR "BOGUSLAVSKA TSL" at 27 Franka Ivana Street, Boguslav city, Obukhiv district, Kyiv region.
Technical Solution 2
New construction of a dual-purpose structure with protective properties of an anti-radiation shelter at the KNP BMR "BOGUSLAVSKA TSL" at 27 Franka Ivana Street, Boguslav city, Obukhiv district, Kyiv region.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]