Description of the project
1. Relevance of the project. Children living in remote rural settlements, as well as students with special educational needs, including 3 children who use wheelchairs or have musculoskeletal disorders, study in educational institutions of the Novoukraine City Council. The existing bus fleet is partially worn out and outdated. This limits access to quality education, creates an additional burden on parents, and contradicts the principle of equal opportunities enshrined in the legislation of Ukraine. 2. Project goal. Creating safe and comfortable conditions for transporting students from rural areas and children with disabilities to educational institutions by purchasing a specialized school bus equipped with modern accessibility features. 3. Project objectives. To purchase a specialized school bus with a lift for transporting students in wheelchairs. To ensure daily safe transportation of children, including those with special educational needs. To update the bus fleet, increasing the level of safety and reliability of transport. To create equal conditions for access to quality education for students from rural areas. 4. Expected results. Organization of daily transportation of 3 students with musculoskeletal disorders in comfortable conditions. Ensuring transportation of schoolchildren from rural areas to the support institution. Increasing the level of accessibility and inclusiveness of the educational process. Reducing social inequality and increasing the level of integration of children with disabilities into the school environment. Optimizing the operation of the bus fleet and reducing costs for maintaining outdated transport. The implementation of the project will ensure equal access to quality education, create comfortable and safe conditions for transporting students, contribute to the development of an inclusive educational environment and comply with state policy in the field of supporting children with special educational needs.
The purpose of the project
Main Goal:
Ensuring inclusiveness and equal opportunities
Secondary Goal:
Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
4 human
Number of people who will use the service
26 human
Number of users from low-mobility population groups
3 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Unhindered access to quality education - school buses
Strategic document
Стратегія розвитку територіальної громади
Task
47 Purchase of a school bus to transport children from the Voronivskyi Starostat
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Purchase of a specialized school bus
Technical Solution 2
• Purchase of a minibus adapted for children with disabilities
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]