Reconstruction of the pumping station of the 2nd lift with the replacement of pumping units and control cabinets, at the address: Poltava region, Vilna Tereshkivka village, Velyky Shlyakh st., 205
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
This project involves replacing the main pumping units (PU) on the second stage of the water treatment plant (which operate on a rather unusual voltage of 690V) with new modern PUs with control cabinets operating on a standard voltage of 380V. As a result of replacing the existing pumps, it is expected to save 10% on electricity consumption, which is about 180 thousand kWh/year. Also, as a result of replacing the PUs, the problem of water supply to consumers during blackouts will be solved, since the existing generator with an output voltage of 380V will be able to ensure the operation of new pumping units during power outages. Currently, this generator powers auxiliary PUs that cannot fully provide consumers with drinking water.
The purpose of the project
Main Goal:
Introducing innovations and energy-efficient solutions
Secondary Goal:
Increasing compliance with modern standards, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
230000 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
State Strategy for Regional Development for 2021–2027
Task
Tasks in the direction of "Comfortable Communities", item 14 Strategic goal "Increasing the level of competitiveness of regions", Operational goal 1. Infrastructure resilient to security, social and economic challenges
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Replacement of the existing 2 pumping units with modern ones
Technical Solution 2
Replacement of existing pumping units with a cascade type pumping station based on 4 pumps
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]