Reconstruction of the heating network from TK704 to the consumer's TK and from the consumer's TK to a residential building on 189/1 Samiyla Kishky Street in Cherkasy


Sector
Municipal infrastructure and services
Stream
Restoration, modernization and development of centralized and decentralized heating systems
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project envisages the reconstruction of the external heat supply network to residential building No. 189/1 on Samiyla Kishky Street with its removal outside the allocated land plot

The purpose of the project

Main goal:

Improving the condition of infrastructure

Secondary goal:

Increasing compliance with modern standards, Introducing innovations and energy-efficient solutions, Improving the quality of services

Description of the purpose of the project and ways to achieve it

Ensuring uninterrupted provision of centralized heating and hot water supply services by carrying out reconstruction work on the external heat supply network

Problems and solutions resulting from project implementation

Due to significant physical and corrosive wear and tear, the network experiences frequent bursts, and the network's passage through the allocated land plot and under capital structures makes it impossible to promptly perform emergency and restoration work. The only possible solution to the problem is to perform reconstruction work on the external heat supply network to the residential building No. 189/1 on Samiyla Kishky Street with its removal outside the allocated land plot. The reconstruction work will improve the provision of centralized heating and hot water services to the residents of the residential building No. 189/1 on Samiyla Kishky Street.

Socio-economic context

Indicator

Value

Maintenance costs per year

30 %

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

District Heating

Stream

Restoration, modernization and development of centralized and decentralized heating systems

Strategic document

Стратегія розвитку територіальної громади

Task

DEVELOPMENT AND MODERNIZATION OF URBAN INFRASTRUCTURE

Project objectives

Indicator
Base value
Target value
no hot water service per year
84 day
14 day
reduction of losses in heating networks
28 %
8 %
lack of centralized heating service during the heating season
7 day
0 day

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Economic analysis of the technical solution for the Cats 189_1 project.docx
26.02.2026
12:30:43 UTC

Alternative technical solutions

Technical Solution 1

Reconstruction of the external heating network to residential building No. 189/1 on Samiyla Kishky Street

Technical Solution 2

Implementation of low-temperature network technology

Total costs4'885'000 UAH9'725'000 UAH
  • For preparation
  • 300'000 UAH550'000 UAH
  • For implementation
  • 4'500'000 UAH9'000'000 UAH
  • For operation
  • 40'000 UAH25'000 UAH
  • For closing
  • 45'000 UAH150'000 UAH
    Average annual costs40'000 UAH25'000 UAH
    Project duration, incl.6 months21 months
  • Deadline for developing a FFS
  • 2 months12 months
  • Implementation period
  • 4 months9 months
    Service life300 months600 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, both national and international

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget4'885'000 UAH9'725'000 UAH
    Capital costs4'885'000 UAH9'725'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation300'000 UAH550'000 UAH
    For implementation4'500'000 UAH9'000'000 UAH
    For operation40'000 UAH25'000 UAH
    For closing45'000 UAH150'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service Unitотримувач послуги
    Service Unit Cost15'000 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - communication with stakeholders

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic feasibility study - technical expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - working with international financial organizations (IFOs)

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    Yes, successfully implemented 1 or more similar projects

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    None of the options are applicable
    Is there an understanding of where to find relevant experts and consultants?
    Yes, negotiations are already underway.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Risk assessment

    Financial riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    26/02/2026SP-L-260226-F7F78CC9Community SPInvestment Feasibility StudyInclude-
    02/03/2026SPP-L-020326-11BBBEB5Community SPPInvestment Feasibility StudyInclude-