- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project provides for major repairs to the landscaping of the territory:
replacement of existing paving and curbs, uprooting of trees and bushes, dismantling of flower beds, landscaping, planting of trees and bushes, installation of benches and garbage cans, installation of lighting of the territory.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Maintenance costs per year
800000 UAH
Number of IDP users
350 human
Number of people who will use the service
16000 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Urban planning and landscaping
Stream
Development of public space infrastructure in populated areas
Strategic document
Регіональна стратегія розвитку
Task
1.2.2 Tourism promotion of the region, support for innovative projects, events that shape the image of the region
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major renovation of the territory of the "Mykhailivsky" park on Bohdan Khmelnytskyi Street in the city of Lyuboml, Kovel district, Volyn region
Technical Solution 2
Reconstruction of the landscaping of the territory of the "Mykhailivsky" park on Bohdan Khmelnytskyi Street in the city of Lyuboml, Kovel district, Volyn region
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]