Reconstruction of building No. 3 of Kostopil Lyceum No. 1 named after T.G. Shevchenko for a dining room, a PRU and an assembly hall.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
Kostopil Lyceum No. 1 named after T.G. Shevchenko of the Kostopil City Council operates in a mixed form of education due to the lack of anti-radiation shelter. The institution uses shelters located within a radius of 500 meters from the institution, which we rent under a contract, which is extremely difficult for students. The shelters that we rent do not meet the needs of the institution, so we need to have a shelter that will ensure full-fledged education for students and save the lives of students and teachers. The second big problem is the lack of a canteen in the lyceum, which has 700 children. The lyceum cannot qualitatively implement the Resolution of the Cabinet of Ministers of Ukraine dated March 24, 2021 No. 305 "On Approval of the Norms and Procedure for Organizing Catering in Educational Institutions and Children's Health and Recreation Institutions". The project envisages the reconstruction of building No. 3, which is not used due to its condition, as a PRU, a dining room and an assembly hall, which will ensure the provision of high-quality educational services, the organization of full-fledged meals for students, and the creation of safe conditions for participants in the educational process.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capital expenditure per year
57 mln UAH
Operating expenses per year
1.5 mln UAH
Maintenance costs per year
300 thous. UAH
Number of IDP users
20 human
Number of jobs, including for IDPs
2 human
Number of people who will use the service
700 human
Number of employees of the institution/institution/organization
70 human
Number of users from low-mobility population groups
1 human
Capacity
520 human
Number of IDPs in the geographical area of impact of the project
100 human
Population in the geographical area of influence of the project
3300 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Ensuring access to high-quality and safe food in educational institutions through the development of modern canteen infrastructure (food blocks)
Strategic document
Стратегія розвитку територіальної громади
Task
3.1.1. Ensuring equal access to quality preschool, general secondary and extracurricular education.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Comprehensive modernization of building No. 3 for a dining room
Technical Solution 2
Construction of the dining hall building of Kostopil Lyceum No. 1 named after T.G.Shevchenko
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]