Public investment project to ensure high-quality, modern and accessible general secondary education “New Ukrainian School”
Sector
Education and science
Stream
Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Maturity level
90
Project Status
Preliminary Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Investment Feasibility Study
Implementation
Completion
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
Public investment project to ensure high-quality, modern and accessible general secondary education “New Ukrainian School”
The purpose of the project
Main Goal:
Improving the quality of services
Secondary Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
The "New Ukrainian School" project aims to create an educational environment that meets modern requirements, promotes the development of the student's personality, and prepares him for the challenges of the modern world. This is an important step in reforming the education system of Ukraine and increasing its competitiveness at the international level.
Problems and solutions resulting from project implementation
1. Improving the educational process
Modern equipment: Introduction of new technologies, such as interactive whiteboards, computers, projectors, which promotes interactive learning and student engagement.
Multimedia resources: Access to electronic textbooks, online courses and other educational materials, which improves the quality of education.
2. Comfortable learning conditions
Renovation of premises: Renovation of classrooms, corridors, bathrooms, which provides comfortable conditions for students to study and stay at school.
Safe environment: Implementation of security systems, such as video surveillance, which ensures the safety of students and staff.
3. Involvement of students and parents
Increased interest: Modern educational materials and equipment increase students' motivation to study.
Active participation of parents: Involving parents in the process of updating the material base helps to strengthen ties between the school and families.
4. Inclusive Education
Adaptation for students with special needs: Updating the material base includes creating a barrier-free environment and providing special learning aids for students with special needs.
5. Saving resources
Energy efficiency: Introducing energy-efficient technologies, such as LED lighting and modern heating systems, which reduces utility costs.
Cost optimization: Reducing maintenance costs for old equipment and premises.
Socio-economic context
Indicator
Value
Number of people who will use the service
2500 human
Number of IDP users
100 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Strategic document
Стратегія розвитку територіальної громади
Task
2 2.3.1. Modernization of educational institutions and preschools, including innovative equipment
Project objectives
Project objectives were not specified by the initiator
Project Sustainable Development Goals
Demand for the service and its dynamics
Indicator
Year
Demand
Annual demand for services/infrastructure
26
2500 human
Annual demand for services/infrastructure
27
2580 human
Economic justification
Alternative technical solutions
Technical Solution 1
Public investment project to ensure high-quality, modern and accessible general secondary education “New Ukrainian School”
Technical Solution 2
Purchasing teaching aids
Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)1'599'000 UAH1'599'000 UAH
For preparation1'000 UAH1'000 UAH
For implementation1'598'000 UAH1'598'000 UAH
Project operation and closure cost2'000 UAH2'000 UAH
For operation1'000 UAH1'000 UAH
For closing1'000 UAH1'000 UAH
Average annual costs1'000 UAH1'600'000 UAH
Project duration, incl.2 months3 months
Deadline for developing a FFS1 month1 month
Implementation period1 month2 months
Service life60 months1 month
Target indicatorsDefined Defined
Technical Solution Status
Active
[The technical approach was selected for further detailed analysis or implementation.]
Rejected
[The technical approach was not selected for further detailed analysis or implementation.]
Financial justification
Total project budget
Total preliminary budget1'601'000 UAH1'601'000 UAH
Project cost (preparation and implementation)1'599'000 UAH1'599'000 UAH
For preparation1'000 UAH1'000 UAH
For implementation1'598'000 UAH1'598'000 UAH
Project operation and closure cost2'000 UAH2'000 UAH
For operation1'000 UAH1'000 UAH
For closing1'000 UAH1'000 UAH
Average project cost per service recipient
Service Unitмодернізоване обладнання
Service Unit Cost640 UAH
Profitability of the project
Is the project expected to generate income?NoNo
Is the project self-sustaining?No
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Source and MechanismYesNo
Management Rationale
Risk assessment
Financial riskDefinedUndefined
Project Approval History
DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
24/09/2025SP-L-240925-0CB9C22DCommunity SPInvestment Feasibility StudyCancellation of the decision to include in a joint venture--
28/10/2025SPP-L-281025-0CAA2F1BCommunity SPPInvestment Feasibility StudyInclude-90