Sector
Transport Sector
Stream
Модернізація та розвиток вулично-шляхової мережі та штучних споруд міста (мости та шляхопроводи) з урахуванням принципів доступності та гендерних підходів
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Regional level of SP
Implementation
Completion
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
Miska St. is a main street of city-wide importance, part of the Great Ring Road around Kyiv, which is used for traffic, including transit transport. The street is in unsatisfactory technical condition. The overhaul involves bringing the technical and geometric parameters of the street into line with the requirements of regulatory documents, making changes to the traffic organization scheme to increase the capacity of the streets and improve the safety of all road users.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Miska Street is a main street of city-wide importance, part of the Great Ring Road around Kyiv, which is used by transit vehicles in particular. The street is in an unsatisfactory technical condition. The overhaul involves bringing the technical and geometric parameters of the street into line with the requirements of regulatory documents, making changes to the traffic management scheme to increase the capacity of the streets and improve the safety of all road users.
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capital expenditure per year
148000 thous. UAH
Strategic Case
Strategic feasibility of the project
Sector
Transport Sector
Subsector
Road transport and road infrastructure
Stream
Модернізація та розвиток вулично-шляхової мережі та штучних споруд міста (мости та шляхопроводи) з урахуванням принципів доступності та гендерних підходів
Strategic document
Стратегія розвитку територіальної громади
Task
Завдання 2.3 Модернізація та розвиток вуличношляхової мережі та штучних споруд міста (мости та шляхопроводи) з урахуванням принципів доступності та гендерних підходів
Project objectives
Project objectives were not specified by the initiator
Project Sustainable Development Goals
Economic justification
Alternative technical solutions
Technical Solution 1
MAJOR REPAIR OF MISKOI STREET FROM PALLADINA AVENUE TO KYIV-GOSTOMEL ROAD
Technical Solution 2
Reconstruction of Miskoy St. from Palladina Ave. to Kyiv-Gostomel Road
Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)538'387'434 UAH699'903'664 UAH
For preparation11'183'100 UAH14'538'030 UAH
For implementation527'204'334 UAH685'365'634 UAH
Project operation and closure cost0 UAH0 UAH
Average annual costs53'838'743 UAH0 UAH
Project duration, incl.19 months40 months
Deadline for developing a FFS7 months16 months
Implementation period12 months24 months
Service life120 months120 months
Target indicatorsDefined Defined
Technical Solution Status
Active
[The technical approach was selected for further detailed analysis or implementation.]
Rejected
[The technical approach was not selected for further detailed analysis or implementation.]
Components of a technical solution
Financial justification
Total project budget
Total preliminary budget538'387'434 UAH699'903'664 UAH
Project cost (preparation and implementation)538'387'434 UAH699'903'664 UAH
For preparation11'183'100 UAH14'538'030 UAH
For implementation527'204'334 UAH685'365'634 UAH
Project operation and closure cost0 UAH0 UAH
For operation0 UAH0 UAH
For closing0 UAH0 UAH
Average project cost per service recipient
Service UnitЗагальна кошторисна вартість об'єкту
Service Unit Cost538'387'434 UAH
Profitability of the project
Is the project expected to generate income?NoNo
Is the project self-sustaining?No
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Source and MechanismYesNo
Funding Sources
Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH
Project Approval History
DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
28/04/2026SP-R-280426-F9CFB252Regional SPInvestment Feasibility StudyInclude--