Arrangement of safe conditions (fire protection): major repairs (installation of fire alarm and lightning protection) of the buildings of the Brody Lyceum of the Ratnivka Village Council at the address: Volyn region, Kovel district, Brody village, Ozerna st., 4
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
An educational institution is an environment where a large number of children, teaching and other employees stay and requires reliable protection from possible emergencies.
The project involves the installation of a fire alarm system, automatic fire notification and evacuation management of participants in the educational process.
The need for the implementation The project arose due to the increased risk of fire hazards due to martial law and emergency situations (terrorist threat, malicious actions of third parties).
The implementation of the project solves the problem of increasing the level of security in the institution, timely notification and management of the evacuation of participants in the educational process in the event of an emergency and compliance with the requirements of modern safety standards.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Increasing compliance with modern standards, Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
1 human
Number of people who will use the service
320 human
Number of employees of the institution/institution/organization
55 human
Population in the geographical area of influence of the project
1500 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Arrangement of safe conditions in institutions providing general secondary education (fire protection)
Strategic document
Регіональна стратегія розвитку
Task
4.5. Educational infrastructure
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs (installation of fire alarm and lightning protection) of the buildings of the Brody Lyceum of the Ratnivka Village Council at the address: Volyn region, Kovel district, Brody village, Ozerna st., 4
Technical Solution 2
Partial installation of a fire alarm system. Use of autonomous fire detectors (sensors) without a centralized system
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]