Providing secondary education institutions of the Kobelyak City Council with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project is aimed at creating a modern educational environment of the educational institution, updating the material and technical base by purchasing modern teaching aids, educational equipment, furniture for the classroom, didactic materials, models and STEM equipment. The implementation of the project will ensure the formation of a competent educational space, improving the quality of educational services, creating comfortable conditions for student learning, and will also contribute to the effective implementation of state standards for primary and basic secondary education. The project will be implemented on the basis of the Oles Honchar Kobelyak Lyceum No. 2, which will have the status of a gymnasium with a primary school from 2027. It is planned to equip a chemistry and biology classroom. Repair work on classrooms will be carried out at the expense of the local budget.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Increasing compliance with modern standards, Improving the quality of services, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Maintenance costs per year
2000 UAH
Number of employees of the institution/institution/organization
2 human
Number of people who will use the service
338 human
Number of IDP users
20 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Strategic document
Стратегія розвитку територіальної громади
Task
1.1.1 Formation of an accessible and effective network of educational institutions (lyceums, specialized high schools, primary and basic schools): - modernization of classroom equipment, creation of media libraries, resource rooms, provision of distance learning facilities and high-speed Internet, etc.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Providing the secondary education institution of the Kobelyach City Council with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Technical Solution 2
Providing the Svitlogirsky Lyceum of the Kobelyak City Council with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]