Construction of water supply networks in the village of Kolodyste, Ladyzhyn rural territorial community, Uman district, Cherkasy region


Sector
Municipal infrastructure and services
Stream
Construction of water supply networks
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SP
Implementation
Completion

General information

Description of the project

The project "Construction of water supply networks in the village of Kolodyste, Ladyzhynsk rural territorial community, Uman district" involves the creation of a new (replacing the old) water supply infrastructure to provide the village residents with high-quality drinking water of appropriate quality. The main stages of the project include organizing and conducting a tender and concluding a contract with the winner for the performance of construction work, carrying out construction work on laying pipelines and installing the necessary equipment. The main goal of the project is to provide the population with drinking water of quality, in accordance with the requirements of the state standard, to preserve health, improve conditions and increase the standard of living of the population. Providing the population with drinking water is one of the priority problems, the solution of which is necessary for the health, improvement of conditions and improvement of the quality of life of the population. The water supply system of the village of Kolodyste was built in the 60s of the last century and is serviced by the Municipal Enterprise "Ladyzhynskyi silkomungosp". Part of the population uses water from artesian wells and wells. However, laboratory control of wells in household diseases indicates that the water in them does not meet sanitary requirements. The presence of nitrates in drinking water threatens the occurrence of pathogenic diseases of the circulatory system, especially in children, who are most vulnerable to poisoning by nitrate compounds. This situation forces the population to buy water in stores, the allocation of funds in the village council budget does not allow to meet the needs of the population in imported water. The implementation of the works envisaged by the project allows for guaranteed priority water supply to the population for drinking, physiological, sanitary and hygienic and household needs, ensures the saving of water resources, which in due time. contribute to improving the standard of living and health of people. The implementation of the project provides an opportunity to solve the problem of rational use of drinking water, scientifically based standardization of drinking water quality, standards for its consumption and formation of tariffs for centralized water supply, requirements of state drinking water standards, maintaining an optimal balance of the use of surface and substandard waters, as well as methods for assessing relevant technologies, technologies, means and methods adopted in the European Union. 

The purpose of the project

Main goal:

Improving the equality of wealth distribution

Secondary goal:

Improving the quality of services

Description of the purpose of the project and ways to achieve it

The project was created to ensure high-quality and round-the-clock water supply to residents of the village of Kolodyste, through the construction of new water supply networks with a length of 21 km. currently in the village of Kolodyste, the centralized water supply system is only partially functioning. The main part of the population uses individual mine wells and boreholes. Old pumping equipment consumes excessive amounts of electricity with minimal efficiency. The implementation of the project will help minimize the accident rate and reduce technological water losses in networks, which is critically important in conditions of water resource shortage, reduce the cost of services for the population by introducing energy-saving technologies and automating accounting processes.

Problems and solutions resulting from project implementation

Due to climate change and the decline in groundwater levels, traditional mine wells of residents are drying up. This leaves a significant part of households without basic access to water. Water in existing decentralized sources has an increased content of nitrates and iron, which negatively affects the health of the population, especially children and the elderly. Due to the lack of a centralized network and hydrants, it is impossible to quickly eliminate fires in the village, which threatens the property and lives of citizens. Implementation of the project to build new water supply networks will ensure the transformation of the living space of the village: Ensuring a stable water supply for all households in the village and social facilities. Reducing the risk of infectious and chronic diseases through the consumption of purified water that meets the DSanPiN standard. Reducing the household burden on residents, especially in households where water delivery was carried out manually. Construction of new networks from modern pipes with a service life of over 50 years. Only the construction of new street water supply networks made of modern materials and the installation of automated wells will ensure the village's vitality and compliance with state quality of life standards.

Socio-economic context

Indicator

Value

Number of people who will use the service

1208 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Water supply and sanitation

Stream

Construction of water supply networks

Strategic document

Стратегія розвитку територіальної громади

Task

2.1.1. Забезпечення населених пунктів водопостачанням

Project objectives

Indicator
Base value
Target value
Length of constructed water supply networks in the village of Kolodyste
0 km
21 km

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

poll
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

No
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
120100 m3
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
project.pdf
03.03.2026
07:12:57 UTC

Alternative technical solutions

Technical Solution 1

Construction of water supply system from polyethylene pressure pipes

Technical Solution 2

Dismantling of existing submersible pumps

Total costs16'300'000 UAH16'300'000 UAH
  • For preparation
  • 700'000 UAH700'000 UAH
  • For implementation
  • 11'700'000 UAH11'700'000 UAH
  • For operation
  • 2'900'000 UAH2'900'000 UAH
  • For closing
  • 1'000'000 UAH1'000'000 UAH
    Average annual costs36'000 UAH36'000 UAH
    Project duration, incl.12 months12 months
  • Deadline for developing a FFS
  • 1 month1 month
  • Implementation period
  • 11 months11 months
    Service life600 months600 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Unsuccessful

    [The technical approach was analyzed and considered for implementation but was not selected as the final option.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget16'300'000 UAH16'300'000 UAH
    Capital costs16'300'000 UAH16'300'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation700'000 UAH700'000 UAH
    For implementation11'700'000 UAH11'700'000 UAH
    For operation2'900'000 UAH2'900'000 UAH
    For closing1'000'000 UAH1'000'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Investment Feasibility Study]
    No
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service Unitвартість на одного абонентавартість на одного абонента
    Service Unit Cost12'086 UAH12'086 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Yes – the analysis was conducted, it was found that the tariffs correspond to the financial capabilities of consumers

    [Response was provided in the Preliminary Investment Feasibility Study]

    Yes – the analysis was conducted, it was found that the tariffs correspond to the financial capabilities of consumers

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesYes

    Funding Sources

    Approved Funds9'500'000 UAH0 UAH
    Expected Funds14'600'000 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Preliminary Investment Feasibility Study]

    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    03/03/2026SP-L-030326-E17CC9C3Community SPInvestment Feasibility StudyInclude-