Modernization of the network of modern preschool education in accordance with the current needs of the community, ensuring quality and comfortable conditions for conducting the educational process


Sector
Education and science
Stream
Modernization of the network of modern preschool education in accordance with the current needs of the community, ensuring quality and comfortable conditions for conducting the educational process
Maturity level
76
Project Status
Preliminary Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Investment Feasibility Study
Implementation
Completion

General information

Description of the project

The project involves the construction of a new preschool education facility for 75 places in the village of Hryshkivtsi. The implementation will ensure access to a safe and high-quality educational environment for all preschool children in the community, taking into account the needs of children with disabilities and internally displaced persons. The expected result will be a reduction in the queue for kindergartens, the creation of 20 jobs and an improvement in the quality of educational services

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Secondary Goal:

Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Creation of new jobs through project implementation

Description of the purpose of the project and ways to achieve it

Problems and solutions resulting from project implementation

Measures to solve the problem 1. Construction of a new preschool educational institution for 75 places using modern energy-efficient technologies. Pre-project preparation: Ordering a sketch of the future preschool educational institution Carrying out work on allocating a land plot, since it is not easy to find free land in Hryshkivtsi due to the population density of the suburban area Development and approval of design and estimate documentation; Passing an examination; Determining sources of co-financing (local budget, SFRD, international grants, partnership programs). 3. Direct implementation of construction work 4. Landscaping, creation of play, sports and recreational areas; 5. Arrangement of shelter, heating, ventilation systems, video surveillance. 6. Equipping with modern equipment: • furniture, educational and developmental aids, kitchen, laundry, medical unit; • creation of an inclusive environment and STEM zone for preschoolers. 7. Personnel and organizational training: formation of a staff of competent employees; training of teachers.

Socio-economic context

Indicator

Value

Number of people who will use the service

75 human

Number of IDP users

10 human

Number of users from low-mobility population groups

5 human

Number of employees of the institution/institution/organization

20 workplaces

Number of IDPs in the geographical area of impact of the project

20 human

Population in the geographical area of influence of the project

5000 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

Preschool education

Stream

Modernization of the network of modern preschool education in accordance with the current needs of the community, ensuring quality and comfortable conditions for conducting the educational process

Strategic document

Стратегія розвитку територіальної громади

Task

2.1.1 Modernization of the network of modern preschool and general secondary education in accordance with the current needs of the community, ensuring quality and comfortable conditions for conducting the educational process

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Дані персоніфікованого обліку дітей дошкільного віку та наявність черги у заклад дошкільної освіти
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
80 human
Annual demand for services/infrastructure
2
80 human
Annual demand for services/infrastructure
3
75 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

Envisaged training or advanced training for women in the private sector
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Alternative technical solutions

Technical Solution 1

Modernization of the network of modern preschool education in accordance with the current needs of the community, ensuring quality and comfortable conditions for conducting the educational process

Technical Solution 2

Creating branches or short-term groups

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)101'340'400 UAH96'000'000 UAH
For preparation1'000'000 UAH1'000'000 UAH
For implementation100'340'400 UAH95'000'000 UAH
Project operation and closure cost2'000'000 UAH2'000'000 UAH
For operation1'000'000 UAH1'000'000 UAH
For closing1'000'000 UAH1'000'000 UAH
Average annual costs51'670'200 UAH4'000'000 UAH
Project duration, incl.30 months13 months
Deadline for developing a FFS6 months1 month
Implementation period24 months12 months
Service life1200 months360 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget103'340'400 UAH98'000'000 UAH
Project cost (preparation and implementation)101'340'400 UAH96'000'000 UAH
For preparation1'000'000 UAH1'000'000 UAH
For implementation100'340'400 UAH95'000'000 UAH
Project operation and closure cost2'000'000 UAH2'000'000 UAH
For operation1'000'000 UAH1'000'000 UAH
For closing1'000'000 UAH1'000'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Average project cost per service recipient

Service Unitкількість отримувачів
Service Unit Cost1'476'291 UAH

Profitability of the project

Is the project expected to generate income?NoNo
Is the project self-sustaining?No

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Partially, we have limited experience

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Management rationale - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Is there an understanding of where to find relevant experts and consultants?
Yes, negotiations are already underway.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Other riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project require preparation assistance from Project Preparation Programs (PPF)?

None of the options are applicable
Need for financing

Does the project require additional funding for preparation?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
06/11/2025SP-L-061125-C9335730Community SPPreliminary Investment Feasibility StudyInclude--
17/11/2025SPP-L-171125-652B7C3BCommunity SPPPreliminary Investment Feasibility StudyInclude-76