New construction of artesian wells on the territory of the Lozova urban territorial community of the Kharkiv region, namely: the city of Lozova, Stepova Street - 2 units, the village of Krasnopavlivka - 2 units, the village of Lymanivka - 1 unit, the village of Yakovlivka - 1 unit, the village of Domakha - 1 unit, the village of Katerynivka - 1 unit with the arrangement of water treatment stations and branching of networks connecting to centralized water supply systems
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project envisages providing the community with an alternative backup source of water supply by drilling 8 deep wells. Instead of repairing kilometers of old pipes, local water supply nodes will be built around new wells, which is much cheaper to maintain. The expected result is autonomous access to clean water and independence from centralized networks.
The purpose of the project
Main Goal:
Creation of new facilities and services
Secondary Goal:
Improving the equality of wealth distribution, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
75630 human
Capacity
8350 m3
Population in the geographical area of influence of the project
77722 human
Number of IDPs in the geographical area of impact of the project
13567 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Регіональна стратегія розвитку
Task
2.2.3. Increasing the availability of high-quality water supply by implementing measures to reconstruct water supply, drainage and treatment systems, reduce discharges and eliminate sources of pollution.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
New construction of artesian wells on the territory of the Lozova urban territorial community of the Kharkiv region, namely: the city of Lozova, Stepova Street - 2 units, the village of Krasnopavlivka - 2 units, the village of Lymanivka - 1 unit, the village of Yakovlivka - 1 unit, the village of Domakha - 1 unit, the village of Katerynivka - 1 unit with the arrangement of water treatment stations and branching of networks connecting to centralized water supply systems
Technical Solution 2
Modernization of existing mine wells (Public wells)
[The technical approach was selected for further detailed analysis or implementation.]
[The project initiator has not taken any decision about this alternative technical approach.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]