Reconstruction (carrying out work to prepare for the heating season and implementing energy saving measures) of the heating system of Secondary School No. 13 at 13 Rosvyhivska Street in Mukachevo
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The reconstruction of the heating system of Secondary School No. 13 involves preparation for the heating season and the implementation of energy-efficient measures. The project addresses the critical need for stable heat supply to the educational institution and reduction of energy consumption. The existing system is worn out, which leads to heat loss, high costs and the risk of disruption of the educational process during the heating season. The implementation of the project will provide comfortable conditions for students and staff, reduce energy costs and increase the environmental friendliness of operation. It is expected to increase thermal efficiency, save resources and improve the infrastructure of the institution.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
1033 human
Number of employees of the institution/institution/organization
94 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Modernization of energy supply infrastructure of secondary education institutions
Strategic document
Стратегія розвитку територіальної громади
Task
3.4.1 Improving the efficiency of the network of educational institutions and the quality of educational services
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction (carrying out work to prepare for the heating season and implementing energy saving measures) of the heating system of Secondary School No. 13 at 13 Rosvyhivska Street in Mukachevo
Technical Solution 2
Comprehensive thermal modernization of the building of Secondary School No. 13 at 13 Rosvyhivska Street in Mukachevo with modernization of heat supply systems and introduction of renewable energy sources
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]