Reconstruction with replacement of the existing pressure sewer collector from the sewage treatment plant No. 3 of the village of Zhvyrka, Ivasyuka St., to the sewage treatment plant No. 1 on Makarenka St. (Francescheski Galamay), 2a in the town of Sokal, Chervonohrad district, Lviv region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The construction is located on the territory of the Sokalska AH, Chervonohrad district, Lviv region.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Improving the equality of wealth distribution, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Population in the geographical area of influence of the project
20373 thous. people
Number of IDPs in the geographical area of impact of the project
1040 thous. people
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Стратегія розвитку територіальної громади
Task
2.1.4. Improving water supply and sanitation
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction with replacement of the existing pressure sewer collector from the sewage treatment plant No. 3 of the village of Zhvyrka, Ivasyuka St., to the sewage treatment plant No. 1 on Makarenka St. (Francescheski Galamay), 2a in the town of Sokal, Chervonohrad district, Lviv region
Technical Solution 2
Use of trenchless technologies (pipeline puncture or rehabilitation) from KNS No. 3 of Zhvyrka village, Ivasyuka st., to KNS No. 1 on Makarenka st. (Francescheski Galamay), 2a in Sokal town, Chervonohrad district, Lviv region
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]