Reconstruction of heating networks from VT 819-1/7 to VT 819-1/9 on Ozerna Street in Mykolaiv


Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of district heating systems
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SP
Implementation
Completion

General information

Description of the project

The project envisages construction work on the reconstruction of heating networks along Ozerna Street in one turn. The laying of the heating main is envisaged along Ozerna Street along existing reinforced concrete trays with backfilling with sand and subsequent backfilling with soil from dumps. The reconstruction of the heating main is envisaged without interfering with existing thermal chambers, supporting and enclosing structures. The laying of heating networks is envisaged without changing the external geometric dimensions of the heating main. 

The purpose of the project

Main goal:

Improving the quality of services

Description of the purpose of the project and ways to achieve it

The pipelines that are subject to reconstruction are the main section for supplying heat energy to consumers. The pipelines are in a state of emergency and require complete replacement. To ensure trouble-free and continuous operation of the heating networks, it is necessary to replace part of the pipelines on Ozerna Street. Pre-insulated pipelines in a polyethylene shell will be used, and shut-off valves for the heating network will be installed. The pipelines are planned to be laid below the depth of soil freezing. The circulation of network water in the heating network is carried out by network pumping units at the heat energy source in which a backup power source is installed. The lowering of the network water of the heating network is carried out at the lower points. Protection of pre-insulated pipelines from additional load is carried out by installing existing unloading reinforced concrete trays under the roadway.

Problems and solutions resulting from project implementation

Problem: The pipelines that are subject to reconstruction are the main section for supplying thermal energy to consumers. The pipelines are in an emergency condition and require complete replacement Solution: To ensure trouble-free and continuous operation of the heating networks, it is necessary to replace part of the pipelines along Ozerna Street

Socio-economic context

Indicator

Value

Number of people who will use the service

21 thous. people

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

District Heating

Stream

Restoration, development and modernization of district heating systems

Strategic document

Стратегія розвитку територіальної громади

Task

2.1.2 Providing heat to community residents

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
316 orders.docx
22.12.2025
12:06:52 UTC

Alternative technical solutions

Technical Solution 1

Reconstruction of heating networks from VT 819-1/7 to VT 819-1/9 on Ozerna Street in Mykolaiv

Technical Solution 2

New construction of part of the heating networks from VT 819-1/7 to VT 819-1/9 along Ozerna Street in Mykolaiv

Total costs13'500'000 UAH26'500'000 UAH
  • For preparation
  • 405'000 UAH1'325'000 UAH
  • For implementation
  • 8'370'000 UAH15'900'000 UAH
  • For operation
  • 2'970'000 UAH5'300'000 UAH
  • For closing
  • 1'755'000 UAH3'975'000 UAH
    Average annual costs140'532 UAH14'053'200 UAH
    Project duration, incl.3 months5 months
  • Deadline for developing a FFS
  • 1 month2 months
  • Implementation period
  • 2 months3 months
    Service life240 months300 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget13'500'000 UAH26'500'000 UAH
    Capital costs13'500'000 UAH26'500'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation405'000 UAH1'325'000 UAH
    For implementation8'370'000 UAH15'900'000 UAH
    For operation2'970'000 UAH5'300'000 UAH
    For closing1'755'000 UAH3'975'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitТеплопостачаня
    Service Unit Cost630 UAH

    Profitability of the project

    Is the project expected to generate income?NoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    No – analysis not performed

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    23/12/2025SP-L-231225-2D56D9E7Community SPInvestment Feasibility StudyInclude-
    30/12/2025SPP-L-301225-F5ADE638Community SPPInvestment Feasibility StudyNot approvedProject cost calculations were not provided in accordance with the MFU order dated 06/23/2025 No. 316, the selected sources of financing were not justified in accordance with the MFU order dated 02/28/2025 No. 131