Major renovation of part of the building at: Cherkasy, Maksym Zaliznyaka St., 93/1 for the complex rehabilitation center for people with disabilities "Zhaga Zhittya" with (PKD)
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project "Overhaul of part of the building at the address: Cherkasy, Maksima Zaliznyaka St., 93/1 for the complex rehabilitation center for people with disabilities "Zhaga Zhittya" (with PKD) is aimed at creating a modern, safe and accessible space for providing complex rehabilitation services to children with disabilities. The implementation of the project involves carrying out a major renovation of the premises taking into account the requirements of barrier-free access, arranging day care groups, specialized rooms for physical, psychological and social rehabilitation, as well as areas for recreation and development. The project is designed to solve the problem of limited access of children with disabilities to quality rehabilitation and social services in the city of Cherkasy, to create conditions for their early development, socialization and support of families. The expected result will be the opening of a modern rehabilitation center, which will provide children with disabilities with the opportunity to receive comprehensive assistance, promote their integration into society and improve the quality of life.
The purpose of the project
Main Goal:
Ensuring inclusiveness and equal opportunities
Secondary Goal:
Improving the quality of services, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
316 units
Number of users from low-mobility population groups
316 units
Strategic Case
Strategic feasibility of the project
Sector
Social sector
Subsector
Rehabilitation Services
Stream
Expanding the capacity of rehabilitation institutions to provide rehabilitation for persons with disabilities
Strategic document
Стратегія розвитку територіальної громади
Task
- Creation of Development Centers (social rehabilitation, employment assistance, etc.) Creation of Development Centers - professional rehabilitation for people with disabilities.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major renovation of part of the building at: Cherkasy, Maksym Zaliznyaka St., 93/1 for the complex rehabilitation center for people with disabilities “Zhaga Zhittya” (with PKD)
Technical Solution 2
Current repair
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]