New road construction with the arrangement of landscaping elements along Vitalii Nesterenko Avenue on the section from Tsentralna Street to Skovorody Street in the village of Fontanka, Odessa District, Odessa Region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the new construction of a modern highway along Vitalii Nesterenko Avenue (on the section from Tsentralna Street to Skovoroda Street) with a comprehensive approach to improvement and traffic safety. This is a key infrastructure initiative aimed at creating reliable transport connections in an actively developing area. What exactly is planned to be implemented: Road surface: Installation of capital asphalt concrete road surface designed for modern loads. Pedestrian zone: Construction of sidewalks taking into account the principles of barrier-freeness (arrangement of ramps, tactile tiles). Drainage system: Creation of effective storm sewers to prevent flooding of the roadway and adjacent areas. Lighting and safety: Installation of energy-efficient LED street lighting, application of road markings and installation of appropriate signs. Greening: Arrangement of roadside strips and planting of green plantings to improve the aesthetic appearance and ecological condition. What problems does the project solve: Transport collapse: The lack of high-quality pavement in this area currently limits throughput and complicates the passage of emergency services. Safety residents: The lack of equipped sidewalks forces pedestrians to move along the roadside, which creates a high risk of road accidents. Logistical isolation: Poor connectivity between residential areas (from Tsentralnaya to Skovoroda) hampers the development of local infrastructure and business. Environmental factor: Unorganized drainage leads to soil destruction and discomfort for residents during rainfall. Expected results: Improving mobility: Creating a comfortable and fast connection between the main arteries of the village. Improving safety: Reducing the accident rate by 80% due to the separation of pedestrian and car flows. Economic development: Increasing the investment attractiveness of adjacent land plots and stimulating the development of small businesses. Social effect: Creating an inclusive space convenient for people with limited mobility, parents with wheelchairs, and the elderly.
The purpose of the project
Main Goal:
Creation of new facilities and services
Secondary Goal:
Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Population in the geographical area of influence of the project
8844 human
Strategic Case
Strategic feasibility of the project
Sector
Transport Sector
Subsector
Road transport and road infrastructure
Stream
Development and rehabilitation of internal public road infrastructure
Strategic document
Стратегія розвитку територіальної громади
Task
3.1.1. Reconstruct community roads and modernize traffic interchanges
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
New road construction with landscaping elements along the avenue
Technical Solution 2
Installation of a transitional type of road surface (gravel-sand mixture) without major drainage and sidewalks.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]