General information
Description of the project
The working project is intended to increase the energy efficiency of the centralized heating system of consumers by reconstructing the heating networks from the boiler house "KMK" in the area from the left "wing" of pumping station No. 59 (TRP-59) to consumers, which are residential buildings and buildings in blocks 300-302, which are characterized by high rates of heat energy losses and unsatisfactory technical condition. Additional land acquisition is not required.
The purpose of the project
Main Goal:
Improving the quality of services
Secondary Goal:
Increasing compliance with modern standards, Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
1300 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
District Heating
Stream
Restoration, modernization and development of centralized and decentralized heating systems
Strategic document
Стратегія розвитку територіальної громади
Task
2.5.2 Reducing energy losses/consumption
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Documents
Alternative technical solutions
Technical Solution 1
Energy saving measures. Reconstruction of district heating networks from the KMK boiler house to residential buildings and buildings located in blocks 300-302 in the Metallurgical District of Kryvyi Rih, Dnipropetrovsk region (Left "wing")
Technical Solution 2
Energy saving measures. Reconstruction of district heating networks from the KMK boiler house to residential buildings and buildings located in blocks 300-302 using steel pipelines in the Metallurgical District of Kryvyi Rih, Dnipropetrovsk region (Left "wing")
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]