General information
Description of the project
Creating an accessible and barrier-free environment for people with limited mobility by installing a sanitary facility (toilet) adapted for people with disabilities and a ramp for safe and convenient movement.
The purpose of the project
Main Goal:
Ensuring inclusiveness and equal opportunities
Secondary Goal:
Improving the equality of wealth distribution, Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDPs in the geographical area of impact of the project
2964 human
Population in the geographical area of influence of the project
24464 human
Strategic Case
Strategic feasibility of the project
Sector
Social sector
Subsector
Social services
Stream
Creating new and strengthening existing conditions for the provision of social services in the Mensk community
Strategic document
Стратегія розвитку територіальної громади
Task
3.2.2. Strengthen existing and create new social services in accordance with the Procedure for Determining Community Needs in Social Services
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major renovation of part of the premises of the municipal institution "Mensk Territorial Center for Providing Social Services" of the Mensk City Council in order to create an accessible environment for people with limited mobility.
Technical Solution 2
Using a portable or temporary ramp and installing a ready-made container or modular toilet adapted for people with disabilities.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]