"Overhaul of the water supply system from the water intake "Zolochiv" to Sichovyh Striltsiv Street in the city of Zolochiv, Zolochiv district, Lviv region"
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The water intake "Zolochiv" is located in the southeastern part of the city of Zolochiv in the valley of a small stream of the left tributary of the Zolochivka River. Today, this water intake is represented by four wells, two of which are operational No. 9633/1 and No. 10822/3 with a depth of 70m and 80m, respectively. The wells exploit an aquifer complex in the Upper Cretaceous deposits. The Zolochiv City Council has allocated two land plots with an area of 2.32 hectares and 0.6966 hectares for the water intake site. The design capacity is 4.8 thousand m/day; equipped with deep pumps WILO 200/70, 55 kW, - 2 pcs.
The length of water supply networks in Zolochiv is 78.3 km. The average service life is 45 years. Depreciated - 46 km., dilapidated - 29.35 km., diameter from 20 mm to 200 mm., including the length of water mains - 4.3 km. Depreciated and dilapidated - 1.2 km.; diameter from 150 mm. to 400 mm.
Water from the centralized water supply is used for household and drinking needs by the population, municipal institutions, commercial organizations and for fire prevention purposes, and is also lost due to leaks.
Currently, the productivity of the water intake "Zolochiv" is 22.2 thousand m / month, or 0.74 thousand m / day using water supply networks. At the same time, the main category of consumers (90%) is the population, namely 19,300 residents. The total number of subscribers is 8,686, of which 8,167 are residents, and 519 are legal entities.
The water quality meets the requirements of DSanPiN 2.2.4-171-10 "State sanitary rules and norms. Hygienic requirements for drinking water intended for human consumption."
The project involves the implementation of major repairs to the water supply system, namely the replacement of the existing water supply branch from the first lifting station to the water supply networks along Shashkevycha M. Street and Sichovykh Striltsiv Street. The water supply system is located in the southeastern part of the city. It is planned to replace the existing cast iron pipeline with a water supply network made of polyethylene pipes with a diameter of Du250 with two separate branches B-1 and B-2. Water supply B1 - material: PE100 SDR17 Dn250 pipe L= 680 m. Water supply B2 - material: PE100 SDR17 Dn250 pipe L= 536 m. Water supply switch - material: PE100 SDR17 Dn250 pipe L= 52 m. Total length of the pipeline - 1268 m.
The project also provides for major repairs of existing and installation of additional wells to improve the operational characteristics of the facility. Number of water supply wells - 11 pcs. Fire hydrants - 1 pc.
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Increasing compliance with modern standards, Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Population in the geographical area of influence of the project
20 thous. people
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources.
Strategic document
Стратегія розвитку територіальної громади
Task
3.1.2. Construction and restoration of engineering infrastructure
Project objectives
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Repair of the water supply line from the water intake "Zolochiv" to Sichovykh Striltsiv Street in the town of Zolochiv, Zolochiv district, Lviv region
Technical Solution 2
Modernization of the water supply system from the water intake "Zolochiv" to Sichovykh Striltsiv Street in the town of Zolochiv, Zolochiv district, Lviv region
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]