New construction of the road from Sichovyh striltsiv Street to Hetmanska Street in Khmelnytskyi


Sector
Transport Sector
Stream
Construction of highways and roads
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

Ensuring proper transport and pedestrian connections to the microdistrict by constructing a new passage from Sichovyh Striltsiv Street to Hetmanska Street in the city of Khmelnytskyi with a length of 825 m, which will contribute to improving the accessibility of the territory, increasing road safety and developing urban infrastructure.

The purpose of the project

Main Goal:

Creation of new facilities and services

Description of the purpose of the project and ways to achieve it

The goal of the project is to ensure unhindered and safe transport and pedestrian connections of the microdistrict by building a new road from Sichovyh Striltsiv Street to Hetmanska Street in the city of Khmelnytskyi with a length of 825 m, which will contribute to improving the accessibility of the territory, developing engineering and transport infrastructure and improving the quality of life of residents. The achievement of this goal is envisaged by performing a complex of preparatory and construction works, in particular, arranging the roadway, arranging sidewalks to ensure pedestrian accessibility, building a drainage system (storm sewer), installing outdoor lighting, organizing safe traffic using road signs and markings, as well as landscaping the surrounding area.

Problems and solutions resulting from project implementation

The key problem is the lack of proper transport and pedestrian connections between Sichovyh Striltsiv and Hetmanska streets, which limits the accessibility of the territory and creates unsafe conditions for movement. The existing unorganized passages are in poor condition and do not meet regulatory requirements. The urgency is due to the development of the microdistrict and the growing need for quality infrastructure. If the problem is not resolved, the low level of security will remain, accessibility will be limited, and the development of the territory will be restrained. The implementation of the project will ensure safe and convenient connections, improve the living conditions of residents, and contribute to the development of infrastructure.

Socio-economic context

Indicator

Value

Other economic

825 m

Strategic Case

Strategic feasibility of the project

Sector

Transport Sector

Subsector

Road transport and road infrastructure

Stream

Construction of highways and roads

Strategic document

Стратегія розвитку територіальної громади

Task

B.3. Convenient and modern transport infrastructure

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Прогноз попиту сформовано з урахуванням очікуваного збільшення інтенсивності руху транспорту, розвитку нових житлових і виробничих зон та необхідності підвищення безперебійного транспортного сполучення, що підтверджує обґрунтовану потребу в будівництві нової вулиці.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
825 m
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Getmanskaya Street 825 m.docx
21.04.2026
12:10:30 UTC

Alternative technical solutions

Technical Solution 1

New construction of the road from Sichovyh striltsiv Street to Hetmanska Street in Khmelnytskyi

Technical Solution 2

Do not build a passage from Sichovyh striltsiv Street to Hetmanska Street in Khmelnytskyi

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)34'566'563 UAH2 UAH
For preparation296'213 UAH1 UAH
For implementation34'270'350 UAH1 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Average annual costs1 UAH0 UAH
Project duration, incl.25 months2 months
Deadline for developing a FFS1 month1 month
Implementation period24 months1 month
Service life600 months1 month
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget34'566'565 UAH4 UAH
Project cost (preparation and implementation)34'566'563 UAH2 UAH
For preparation296'213 UAH1 UAH
For implementation34'270'350 UAH1 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitНа даний проєкт відсутні платні послуги
Service Unit Cost1 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
None of the options are applicable
Does the team have experience implementing similar projects?
Partially, we have limited experience

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
22/04/2026SP-L-220426-DC2EA094Community SPInvestment Feasibility StudyInclude--
24/04/2026SPP-L-240426-E59A2EF8Community SPPInvestment Feasibility StudyIncludeThe Investment Council has decided to include the project in the Khmelnytskyi MTG EPP-