General information

Description of the project

The project involves major renovation of the premises of the second floor of the municipal pharmacy of the KNP "Zolochivska TsRL" at the address: 9 Shashkevycha St., Zolochiv, Lviv region, in order to create modern, comfortable and functional conditions for the operation of the institution and provide high-quality pharmaceutical services to the population. The work will include updating internal engineering networks, finishing the premises, replacing windows and doors, increasing energy efficiency, as well as ensuring accessibility for people with limited mobility. The implementation of the project will contribute to improving the material and technical base of the hospital and increasing the level of patient service.

The purpose of the project

Main goal:

Meeting demand

Secondary goal:

Capacity building, Creation of new facilities and services, Improving the equality of wealth distribution, Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

The goal of the project is to create modern, safe and functional conditions for the operation of the municipal pharmacy of the Zolochivska Central Regional Hospital by carrying out a major renovation of the premises on the second floor, which will ensure that the space complies with sanitary and technical standards, increase the level of energy efficiency of the building, improve working conditions for staff and service to visitors, including representatives of low-mobility groups. The project is aimed at improving the quality of pharmaceutical services, rational use of premises and strengthening the material and technical base of the hospital to effectively meet the needs of the community in affordable and high-quality medicines.

Problems and solutions resulting from project implementation

The main problems of the premises on the second floor of the municipal pharmacy are the deterioration of engineering networks, low energy efficiency, outdated interior decoration, lack of proper conditions for storing medicines and insufficient accessibility for people with limited mobility, which complicates the provision of high-quality and comfortable service to visitors. The implementation of the project will allow solving these problems by modernizing engineering systems, insulating and replacing windows and doors, arranging premises in accordance with sanitary and hygienic standards, creating barrier-free access and optimizing planning solutions. As a result, safe and modern working conditions for staff, proper storage of medicines and improving the quality of pharmaceutical services for the community will be ensured.

Socio-economic context

Indicator

Value

Population in the geographical area of influence of the project

50000 human

Strategic Case

Strategic feasibility of the project

Sector

Healthcare

Subsector

Primary healthcare

Stream

Ensuring access to quality medical care through the development and modernization of medical infrastructure facilities

Strategic document

Регіональна стратегія розвитку

Task

2.2.2 High-quality and affordable medical services

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Аналіз статистичних даних, демографічних показників, звернень пацієнтів та динаміки реалізації лікарських засобів у громаді
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
26
100 %
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Economic_analysis_of_the_Zoločiv_pharmacy.docx
21.10.2025
00:01:11 UTC

Alternative technical solutions

Technical Solution 1

Major renovation of the premises on the 2nd floor of the municipal pharmacy of the Zolochivska Central Regional Health Center at the address: 9 Shashkevycha St., Zolochiv, Lviv region.

Technical Solution 2

Relocation of the pharmacy unit to another existing hospital building or to rented commercial space

Total costs1'295'626 UAH550'000 UAH
  • For preparation
  • 10'000 UAH10'000 UAH
  • For implementation
  • 1'205'626 UAH500'000 UAH
  • For operation
  • 40'000 UAH20'000 UAH
  • For closing
  • 40'000 UAH20'000 UAH
    Average annual costs350'000 UAH350'000 UAH
    Project duration, incl.10 months7 months
  • Deadline for developing a FFS
  • 4 months3 months
  • Implementation period
  • 6 months4 months
    Service life300 months120 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, both national and international

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget1'295'626 UAH550'000 UAH
    Capital costs1'295'626 UAH550'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation10'000 UAH10'000 UAH
    For implementation1'205'626 UAH500'000 UAH
    For operation40'000 UAH20'000 UAH
    For closing40'000 UAH20'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service Unit.
    Service Unit Cost0 UAH

    Profitability of the project

    Is the project expected to generate income?YesNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    No – analysis not performed

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    21/10/2025SP-L-211025-128AE105Community SPInvestment Feasibility StudyIncludeInclude in sector portfolio
    03/11/2025SPP-L-031125-14C54A86Community SPPInvestment Feasibility StudyIncludeInclude in the EPP investments of the Zolochiv urban territorial community