General information
Description of the project
The project involves major repairs of the fire alarm system and installation of lightning protection in the "Gymnasium No. 7 of Sambora" educational institution. The goal of the project is to increase the safety of students and staff of the institution, reduce the risk of fires and lightning strikes. As part of the implementation, it is planned to replace outdated equipment with modern fire alarm and alarm systems, install an effective lightning protection system, as well as integrate the system with the institution's existing technical networks. The implementation of the project will ensure timely detection of fire threats, prompt notification of staff and students, reduce potential material damage and health risks, and create a safe environment for children to study and stay. The expected result is a modern, reliable and regulatory-compliant security system for the educational institution.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Improving the equality of wealth distribution, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
354 human
Number of employees of the institution/institution/organization
45 human
Capacity
530 human
Number of IDP users
5 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Arrangement of safe conditions in institutions providing general secondary education (fire protection)
Strategic document
Стратегія розвитку територіальної громади
Task
Operational objective 4.1. Educated community Task 4.1.1 Creating a comfortable and modern learning environment
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs of fire alarm and lightning protection of the "Gymnasium No. 7 of the city of Sambora, Sambir City Council, Lviv region" at 12 Kopernika St., Sambor, Lviv region
Technical Solution 2
Preservation of the existing fire alarm and lightning protection system without modernization
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]