Major repairs of the road surface on 9-a Slobidska Street from Pogranichna Street to Kovalska (Kuznetska) Street in Mykolaiv


Sector
Transport Sector
Stream
Development and restoration of public road infrastructure
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project involves major repairs to the road surface on 9-a Slobidska Street in the section from Pohranychnaya Street to Kovalskaya (Kuznetskaya) Street in Mykolaiv. The work includes the restoration of the carriageway, strengthening of the road surface base, and improvement of the operational characteristics of the road in order to increase traffic safety and comfort for road users.

The purpose of the project

Main goal:

Improving the condition of infrastructure

Secondary goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

The project involves major repairs to the road surface on 9-a Slobidska Street in the section from Pohranychnaya Street to Kovalskaya (Kuznetskaya) Street in Mykolaiv. The work includes the restoration of the carriageway, strengthening of the road surface base, and improvement of the operational characteristics of the road in order to increase traffic safety and comfort for road users.

Problems and solutions resulting from project implementation

It is planned to increase the level of road safety and the level of comfort for residents and guests of the city

Socio-economic context

Indicator

Value

Number of people who will use the service

50000 human

Strategic Case

Strategic feasibility of the project

Sector

Transport Sector

Subsector

Road transport and road infrastructure

Stream

Development and restoration of public road infrastructure

Strategic document

Стратегія розвитку територіальної громади

Task

1.2.1 Increasing safety for all road users

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Major repairs (6) (1) (1).docx
19.12.2025
14:26:24 UTC

Alternative technical solutions

Technical Solution 1

Major repairs of the road surface on 9-a Slobidska Street from Pogranichna Street to Kovalska (Kuznetska) Street in Mykolaiv

Technical Solution 2

Current road surface repairs on 9-a Slobidska Street from Pohranychna Street to Kovalska (Kuznetska) Street in Mykolaiv

Total costs11'114'326 UAH200'000 UAH
  • For preparation
  • 100'000 UAH0 UAH
  • For implementation
  • 11'014'324 UAH200'000 UAH
  • For operation
  • 1 UAH0 UAH
  • For closing
  • 1 UAH0 UAH
    Average annual costs11'114'324 UAH200'000 UAH
    Project duration, incl.9 months4 months
  • Deadline for developing a FFS
  • 3 months1 month
  • Implementation period
  • 6 months3 months
    Service life120 months36 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget11'114'326 UAH200'000 UAH
    Capital costs11'114'326 UAH200'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation100'000 UAH0 UAH
    For implementation11'014'324 UAH200'000 UAH
    For operation1 UAH0 UAH
    For closing1 UAH0 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitВартість на одног окористувача
    Service Unit Cost222 UAH

    Profitability of the project

    Is the project expected to generate income?NoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds11'114'324 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    22/12/2025SP-L-221225-685161D2Community SPInvestment Feasibility StudyInclude-
    30/12/2025SPP-L-301225-449B3775Community SPPInvestment Feasibility StudyInclude-